Reports & recommendations
24 recommendations, each with the government response on the record. Filter by government response or delivery status.
Reports (1)
| Title | Volume | Publication Date | Recommendations | Links |
|---|---|---|---|---|
| Edinburgh Tram Inquiry Report | Final Report | 19 Sep 2023 | 24 |
Recommendations (10)
Business Case Timing
Where the Business Case for any future light rail project is based upon an assumption that, prior to the award of the contract for the construction of the infrastructure, certain matters will have been completed (e.g. design, the obtaining of all necessary approvals and consents or the diversion of utilities), the contract negotiations should be delayed until completion of these matters has been achieved, failing which before any infrastructure contract is signed a new Business Case should be prepared on the basis of the altered assumptions that prevail and should be approved by the promoter and owner of the project.
In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that the Scottish Government and its public bodies "already operate in line with these recommendations and best practice" (Màiri McAllan response, Nov 2023). The Minister noted that while the recommendations were directed at project leads and local authority officials, they linked to work being carried out across the administration and its agencies (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
Optimism Bias in Business Cases
All versions of the Business Case, including any Business Case required as a result of altered assumptions, should include an assessment of risk that takes account of optimism bias in accordance with the current published government guidance.
In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that while the recommendation was directed at project leads and local authority officials, the administration and its public bodies "already operate in line with these recommendations and best practice" (Màiri McAllan response, Nov 2023). The Minister stated that this was evidenced by an established record of delivering major infrastructure projects, including the Queensferry Crossing and Borders Railway (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
External Peer Review
The assessment of risk at each stage mentioned in Recommendation 6 should be the subject of a peer review by external consultants with experience of similar large-scale infrastructure projects in the transportation sector who should submit a report of each review to the promoter and owner of the project as well as to the procurement and project manager sufficiently far in advance of the signature of the infrastructure contract to enable the promoter and owner to consider whether to authorise its signature and, as appropriate, to consider any other available options requiring a strategic decision.
In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that her administration and its public bodies "already operate in line with these recommendations and best practice" across major infrastructure projects (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
Update Optimism Bias Guidance
The existing Guidance on optimism bias was based on empirical data available almost two decades ago and should be revised to take into account the additional data that is now available. In particular, the reference classes should be updated to include a specific reference to light rail projects and the recommended uplifts for the different reference classes should be adjusted to reflect the additional empirical data that is now available. Thereafter the Guidance should be reviewed and revised to take account of additional data on a regular basis at intervals of not more than five years.
In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that the administration follows detailed guidance on procurement, risk, and optimism bias enshrined in the Treasury's Green Book, the Scottish Public Finance Manual, and the Client Guide to Construction Projects (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
Risk Management Standards
The identification and management of risk should be an integral part of the governance of all major public-sector contracts in future. In identifying and managing risk the following principles should be adopted:
• Probabilistic forecasts rather than single-point forecasts should be used to take account of the risk appetite of funders and project sponsors.
• Funders, sponsors and project managers should be cautious when adjusting uplifts and there should be critical review of claims that mitigation measures have reduced project risk.
• Effective governance needs to provide constant challenge and control of the project, including recording of where the project is compared with its baseline, and reacting quickly to get the project back on track, whenever there are signs that it is veering off course. This necessitates providing senior decision-makers with data-driven reports on project performance and forecasts combined with reports by the management team and independent audits.
• In reporting to governance bodies there should be special emphasis on detecting early warning signs that the cost, schedule and benefit risks may be materialising so that damage to the project can be prevented. If early warning signs do emerge, the project should revisit assumptions and reassess risk and optimism bias forecasts.
• The quality of evidence rather than process is the key to providing effective oversight and validation.
In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated that the Scottish Government and its public bodies "already operate in line with these recommendations and best practice" as demonstrated by their delivery of major infrastructure projects (Màiri McAllan response, Nov 2023). In February 2024, the City of Edinburgh Council Transport and Environment Committee agreed that a report would be brought back setting out what funding had been allocated and what measures would be taken regarding recommendation 9 on risk and optimism bias (City of Edinburgh Council, Feb 2024).
Public Fund Protection
The Scottish Ministers and local authorities responsible for funding light rail projects should be mindful at all times of their obligation to protect public funds and to obtain value for public expenditure. In that regard:
• the Scottish Ministers should impose conditions on the payments of grants, similar to the “hold points” imposed on the offer of grant made on 19 March 2007 that enable them to review at each “hold point” whether the scheme is continuing to meet its objectives and to determine whether to continue to support the funding and implementation of the scheme;
• continued financial support from the Scottish Ministers should require their critical review of all versions of the draft Business Case and their approval of the FBC as well as their review, and approval before their signature, of the draft contracts for the delivery of the project;
• the Scottish Ministers should be involved in the delivery of the project as they were before the withdrawal of the support of officials from Transport Scotland in 2007 and following the resumption of infrastructure works after the mediation settlement at Mar Hall; and
• as a condition of the grant the local authority should be obliged to comply with the project monitoring and control procedures of Transport Scotland and should ensure that robust, transparent, externally verifiable project controls for the project are in place.
In November 2023, Cabinet Secretary for Transport, Net Zero and Just Transition Màiri McAllan told the Scottish Parliament that effective collaboration was central to shared priorities under the Verity House Agreement (Màiri McAllan response, Nov 2023). The Minister stated that while delivery responsibility must remain with councils as project leads, she had "absolutely no hesitation in championing close working with our local authority partners" (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
Record Keeping Requirements
For reasons of transparency and accountability for public expenditure, the Scottish Ministers should keep minutes of:
• the nature and content of any discussions and the reasons for any decisions taken at all meetings, discussions or telephone conversations, and in email or other correspondence between a Minister and civil servants relating to the nature and extent of any involvement by civil servants in the procurement and delivery of a project funded or to be funded in whole or in part from public funds (including a grant from the Scottish Ministers);
• all discussions between a Minister and representatives of a local authority, the company responsible for the procurement and delivery of a publicly funded project or the company responsible for its construction to record what was discussed and what, if any, decisions were reached and the reasons for any such decision;
• all discussions between a Minister and civil servants including telephone discussions concerning any negotiations, including, but not restricted to, negotiations at mediation, for settling disputes involving contracts funded or to be funded in whole or in part from public funds (including a grant from the Scottish Ministers) to record what was discussed and what, if any, decisions were reached and the reasons for any such decision.
In November 2023, Cabinet Secretary for Transport, Net Zero and Just Transition Màiri McAllan stated that robust procedures regarding minute-taking and documentation management had long been embedded across the civil service (Màiri McAllan response, Nov 2023). The Minister added that the Permanent Secretary had recently reiterated to a parliamentary committee the commitment to maintaining systems to record and manage this information (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
Utility Diversion Planning
The procurement strategy for any future light rail project should make adequate provision for the uncertainties concerning the location of utilities and redundant equipment belonging to present and past utility companies, particularly in urban centres. In particular, although it is not possible to be prescriptive about the appropriate timescale:
• the procurement strategy should include a requirement that the route of the track should be exposed and cleared of utilities well in advance of the infrastructure contractors commencing their work;
• the procurement strategy should specify the period that should elapse between the exposure and clearance of the route and the commencement of construction, to ensure that the contractors have unrestricted access to the construction site and may proceed with the infrastructure works unencumbered by the presence of utilities; and
• in fixing the period mentioned above, the procurement strategy should take into account the length of the route to be constructed, past experience of the time taken for the diversion of utilities in light rail projects in other parts of the UK and any additional constraints peculiar to the project such as an embargo on work to divert utilities during particular periods such as the festive season or special events (e.g. the Edinburgh Festival).
In November 2023, Cabinet Secretary for Transport, Net Zero and Just Transition Màiri McAllan stated to the Scottish Parliament that the Scottish Government and its public bodies already operated in line with the recommendation and best practice (Màiri McAllan response, Nov 2023). In April 2024, Paul Lawrence, Executive Director of Place at the City of Edinburgh Council, reported that the Council did not accept the recommendation, noting that clearing utilities immediately prior to construction had been effective on the Trams to Newhaven project and should remain an option for future schemes (Paul Lawrence, Apr 2024).
Utility Diversion Risk Management
Although some participants in the Inquiry criticised the use of MUDFA to divert utilities in advance of the infrastructure works and advocated the “bow wave” approach to the diversion of utilities that followed the mediation settlement at Mar Hall, I do not think it appropriate to be prescriptive about how the risks associated with the diversion of utilities are managed. It is sufficient for promoters of light rail schemes to be aware of such risks and to demonstrate that they have adequate proposals for managing them.
In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that the Scottish Government and its public bodies "already operate in line with these recommendations and best practice" through their delivery of major infrastructure projects (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
Interviews of Key Personnel in Readiness Reviews
As part of their investigations, representatives of OGC undertaking an independent “readiness review” of a publicly funded project and representatives of any person, including representatives of any public body such as Audit Scotland, undertaking a review of the progress of and/or expenditure on a project funded in whole or in part by public funds should interview key personnel involved in the project to ensure that each of them understands his or her role and is performing it effectively. In preparing any list of key personnel to be interviewed, the individuals undertaking the investigations shall include the person designated as SRO.
In December 2023, Andrew Kerr, Chief Executive of the City of Edinburgh Council, stated that while the recommendation was for third parties undertaking future reviews or audits, he recommended that the council agree to support any such review or audit to ensure "a clear understanding of roles and responsibilities" (Andrew Kerr response, Dec 2023). The record holds no update since the council's response of December 2023 (Andrew Kerr response, Dec 2023).