Recommendation ETI-5: Business Case Timing
From Edinburgh Tram Inquiry Report, published 19 September 2023.
Recommendation
Where the Business Case for any future light rail project is based upon an assumption that, prior to the award of the contract for the construction of the infrastructure, certain matters will have been completed (e.g. design, the obtaining of all necessary approvals and consents or the diversion of utilities), the contract negotiations should be delayed until completion of these matters has been achieved, failing which before any infrastructure contract is signed a new Business Case should be prepared on the basis of the altered assumptions that prevail and should be approved by the promoter and owner of the project.
In brief (written by this site)
In November 2023, Màiri McAllan, Cabinet Secretary for Transport, Net Zero and Just Transition, stated to the Scottish Parliament that the Scottish Government and its public bodies "already operate in line with these recommendations and best practice" (Màiri McAllan response, Nov 2023). The Minister noted that while the recommendations were directed at project leads and local authority officials, they linked to work being carried out across the administration and its agencies (Màiri McAllan response, Nov 2023). The record holds no update since the Scottish Government's response of November 2023 (Màiri McAllan response, Nov 2023).
Sources
AI-generated summary of the record on this page, checked by a second model and automatic checks, 26 Sep 2026. The record below is the sources' own words.
Government response
The remaining thirteen recommendations cover a range of areas relating to the governance and delivery of light rail projects. While these recommendations are directed squarely at project leads and Local Authority officials, there is a link to much of the work being done by this Government and its agencies, including Transport Scotland.
I am pleased to report that this Government and its public bodies already operate in line with these recommendations and best practice as evidenced by our excellent record of delivering major infrastructure projects including the Borders Railway, the Edinburgh Glasgow Improvement Programme, the Aberdeen Western Peripheral Route and the Queensferry Crossing over the Forth Estuary, a complex engineering feat that has put our workmanship to the front and centre of global engineering.
How this response relates to the recommendation
Site note: The statement gives this passage once, for what it calls "the remaining thirteen recommendations", and does not list them. The site records it on ETI-5, ETI-6, ETI-7, ETI-9, ETI-13 and ETI-14, the recommendations the site addresses to the Scottish Government that the statement does not answer elsewhere.
Delivery
No statement on delivery from Scottish Government has been found in the sources searched (last checked 31 January 2026). This is separate from the response above.