Elliot Burton

PFD Report All Responded Ref: 2021-0131
Date of Report 30 April 2021
Coroner Kevin McLoughlin
Response Deadline ✓ from report 30 June 2021
All 4 responses received · Deadline: 30 Jun 2021
Response Status
Responses 4 of 3
56-Day Deadline 30 Jun 2021
All responses received
About PFD responses

Organisations named in PFD reports must respond within 56 days explaining what actions they are taking.

Source: Courts and Tribunals Judiciary

Coroners Concerns
The site is always unmanned: It is located in a remote area It is known that in the years 2018-2021, young people have trespassed onto the site . July have hear

3. There are deep uncovered channels on the site to conduct water through the facility. It is foreseeable that a trespasser would be in a precarious situation if they were t0 fall into the water , as Elliot Burton did. Many of the channels are uncovered, and Ior have no edge protection_ Despite perimeter fencing; it is known that one route for children to gain entry to the site is by crossing the River Calder at the Kirkthorpe weir adjacent to the site. There are few, if impediments to prevent access to weir from the river bank opposite the site. Despite the passage of some 21 months since Elliot Burton's death, little effective action has been taken to reduce the risk of children being harmed if they are tempted to trespass on this site.
Responses
Wakefield Council
30 Apr 2021
Wakefield Council has implemented several safety measures at Kirkthorpe Weir since August 2019, including enhanced perimeter fencing, a new lockable gate, high-specification CCTV, and reviewed warning signage. They are also planning daily manned security patrols during summer 2021 and designing a new viewing platform with robust physical barriers for improved access control. AI summary
View full response
Dear Mr Mcloughin Rez-_Inquest touching the death of Elliot Peter BURTON (deceased) refer to your letter dated 30th April 2021, and the request to provide a response to the Regulation 28 Report to Prevent Future Deaths: Please find enclosed what is a comprehensive report in full response to the concerns you have raised and recorded in respect of the above case If you require any further information or detail please do not hesitate to contact me.
Yorkshire Hydropower Limited
30 Jun 2021
Yorkshire Hydropower Limited has implemented a range of measures including enhanced perimeter fencing, warning signs, CCTV, internal barriers, gates, and covers to deter unauthorised access. They also provided manned security patrols in summer 2020 and are procuring a contractor for future patrols, while undertaking works to block routes within the facility and cover channels where practicable. AI summary
View full response
Dear HM Senior Coroner Kevin McLoughlin Regulation 28 Report I write on behalf of Yorkshire Hydropower Limited ("YHL") in response to your Regulation 28 report dated 30 April 2021 regarding the death of Elliot Peter Burton at the Kirkthorpe Hydropower Facility on 29 July 2019. I would like to begin by, once again, expressing my condolences to Elliot's family and my sorrow for their loss. The design, planning and construction of Kirkthorpe Hydropower Plant (the "Facility") was concerned with the risks associated with unauthorised access into it. Since the Facility came into our control, we have implemented a wide range of further measures with the aim of reducing and preventing unauthorised access, but recognise that the issues present an ongoing challenge. Present measures include physical deterrents (perimeter fencing, warning signs, CCTV, internal barriers, gates and covers), to community engagement through the local police (to educate and raise awareness). The Facility requires open access to the river, a number of deep-water channels and pools for its operation and systems to reduce debris blockage and ensure its safe removal. As such, steps to further secure and/or cover hazards have to be carefully considered in light of other risks that they may introduce. In response to the evidence heard at the inquest and your comments, a further detailed review of the known routes taken by trespassers has been undertaken, with the assistance of an external health and safety advisor. Turning to the specifics of the Regulation 28 report, I respond to the detailed points raised in section 5.
1. Response to Paragraph (1)
1.1 The Facility was designed to be unmanned. It does not need workers present for operation, which can be monitored and controlled remotely. However, contractors are on site at least 3 times a week to undertake checks and routine maintenance.
1.2 As set out in evidence before the inquest, public safety and site security is aided by extensive CCTV which is monitored by Servo, our security contractors, who can communicate directly via the site PA system and also will make reports to the Police and relevant key holders.
1.3 We are currently trialling having a manned security presence on site between the hours of 10am to 8pm, 7 days a week for the summer months. Primarily the guard is a deterrent. The guard will be limited in challenging trespassers, for example they will not be able to physically remove them from the Facility.

Yorkshire Hydropower Limited Company no. 09076541, C/O RES White Limited, Beaufort Court, Egg Farm Lane, Kings Langley, WD4 8LR Yorkshire Hydropower Limited

1.4 We will review the effectiveness of this at the end of the summer. This review will include consideration of any interactions between the guard and potential or actual trespassers, the personal safety of the guard, whether trespass was deterred and/or incidents prevented and whether the times were aligned with the periods of activity in the locality. The effectiveness and/or necessity of having such a security presence will also be viewed in the context of the other measures being implemented, these are discussed in response to your other paragraphs below.
2. Response to Paragraph (2)
2.1 YHL was subject to a share sale which completed a week prior to Elliot's tragic death. Following the tragedy, all reports were requested from the incumbent security contractors. These reports informed the measures which the board then undertook. However, it was apparent from the evidence at the inquest that a full record had not been provided.
2.2 We recognise that incidents of trespass have been ongoing for some time. Although from a review of all the records the method of entry across the weir was not previously used until the weekend of Elliot's death. The challenges of traversing 90 metres across the weir before climbing over the sluice gates and up and into the Facility meant that this was not a route of access which had previously been anticipated. As described below we have engaged with Wakefield Metropolitan District Council ("WMDC") and Canal and River Trust ("CRT") as the relevant landowners to identify and implement practicable measures to deter access along this route.
2.3 In relation to access from the landside perimeter, we have added further fence panel returns and signage, we have also now had expert advice as to the use of galvanised metal spiked fans. Where practicable these will be used to deter persons from climbing around the edge of perimeter fence panels where they open on to the river and accessing ledges within the Facility. The objective is to make access difficult and unattractive to the Facility as a whole, and within it in relation to those areas where there are drops to deep and potentially fast flowing water. However, these measures must not create debris traps that import significant risk for those required to then remove debris and maintain the structures.
3. Response to Paragraph (3)
3.1 On entry to the Facility, there are a number of uncovered channels. These comprise the screening channel, outlet channel, fish pass and eel pass. There exists edge protection in the form of timber fencing and metal railing in areas where those working in the Facility have to walk. This edge protection is designed to stop the accidental passage of persons into an area of danger, it is not effective at stopping someone who deliberately ignores it, placing themselves in danger.
3.2 The use of fences and barriers within the Facility, as well as the covering of channels has to be considered in the context of debris entrapment and critically, access for those removing it. The force of the river and the substantial debris that collects can and has caused damage to the Facility, this is one of the major operational concerns in this dynamic environment.
3.3 The size of the outlet channel makes any proposal to cover it with decking, steel or other material, difficult to safely install and maintain (the outlet channel cannot be readily drained). Maintenance will bring several operational issues, particularly around the issue of debris which will, in flood conditions, be deposited on top of the decking bringing with it an uncertain loading regime and a requirement to remove it. Such removal would require workers to have to venture onto the decking which might have become damaged or dislodged from the flooding. Anyone falling through such decking would have no ready means to escape. Consequently, it is not considered reasonably practicable to cover a channel of this type and size. Further a cover would only be across the screening channel itself and not the inlet.

Yorkshire Hydropower Limited Company no. 09076541, C/O RES White Limited, Beaufort Court, Egg Farm Lane, Kings Langley, WD4 8LR Yorkshire Hydropower Limited
3.4 We are reducing the attraction of this route at the upstream end by extending the access along the screen walkway to include access over the end of the screenings channel. This would reduce the attraction to climb through/over to see what is beyond. This will be achieved by relocating the existing end handrail and fitting additional mesh decking.
3.5 We have also considered the feasibility of covering the top of the screening channel, between the fish pass bridge and the outlet bridge. The channel is some 750mm wide and would suit open mesh decking. Such decking however would not remove the risk of falling, just transfer it to the fish pass on one side or the outlet channel on the other. Covering the screening channel whilst not removing the risk could encourage people to walk along the decking. To prevent this we have considered hand railing on either side but again this would further suggest that this was a thoroughfare, which it is not. It is therefore not considered prudent to deck this channel as it is likely to increase the trespass risk and dangers associated with it.
3.6 We have in turn also considered covering the fish pass, however the concern is that this could create hazards which do not currently exist. At some 3.69m wide such decking would require substantial support steelwork to support the individual panels. The level at which such decking would be placed would have to vary in line with the varying height of the side walls and differences in level from one side to the other.
3.7 The overall profile would be for the level of the decking to have to fall as the side walls to the fish pass itself fall. The fish pass is frequently submerged during flood conditions, this would present a number of hazards not least that of potentially pulling a person caught in the water beneath the covers. In such a situation any lifejacket or other item that they make take with them (such as an inflatable) would most likely trap a person resulting in drowning. Without covers such a person, whether a canoeist, swimmer or person simply having fallen into the water, would be flushed out downstream with a chance of subsequent rescue.
3.8 In addition, Environment Agency guidance on fish pass design also discourages covers to fish passes as these can cause fish to be hesitant about using them.
3.9 Presently access into this area is restricted by a locked access gate and as described in our response to paragraph 4, plans are in development to install a security fence to the left hand side to prevent access into the Facility from the weir and sluice gates.
3.10 In relation to any cover across a potentially fast flowing channel, debris would be pulled under the covers and then pushed upwards exerting a force against the underside of the covers. Large debris such as sections of trees etc. would produce significant upwards forces with potential to damage the decking and support steelwork. Such decking would require inspection post flood to ensure that it remained intact and safe. This inspection and potential repair work would, in itself, present risks to maintenance teams that do not currently exist. Finally, it is again of general concern that such covers would encourage persons to walk on them creating the perception that this area was safe.
3.11 It is therefore considered that preventing access onto the walls is a preferable method rather than allowing such person onto the walls and then trying to keep them safe.
3.12 With reference to access along the capping beam which encloses the outlet channel, we have had to balance the need for any structures to be robust so as to resist flood impact and also to be reasonably accessible for maintenance (for example through the use of hand tools). We will be installing a galvanised steel fan, bolted to the capping beam and spanning out over the outlet channel.

Yorkshire Hydropower Limited Company no. 09076541, C/O RES White Limited, Beaufort Court, Egg Farm Lane, Kings Langley, WD4 8LR Yorkshire Hydropower Limited
3.13 We are also going to install galvanised steel fans across the wall that boarders the fish pass. This will prevent access to that ledge from each end and also a possible access point adjacent to the turbine house.
3.14 Another area which we have further reviewed is the very downstream end of the outlet, to block this route we will install a further fan located just upstream of the escape ladder, combined with a small panel of fencing.
3.15 Another area which has had interest from trespassers is the high level bridge across the intake penstock which provides operational access to the penstock actuator. Access to the bridge is via a vertical ladder. We will be installing a hinged, and lockable plate, fitted to the ladder to prevent it being climbed by unauthorised persons.
3.16 In overview we have tried to look at access to all areas within the Facility, particularly focussing on where there are drops to channels. Having carefully considered the feasibility of covering them, we have determined that to do so will introduce other risks that are more likely to result in an incident with the consequence of serious injury. Covering the channels may guard against one risk, but in practice will create a greater exposure to danger. The series of fans and gates present a more effective and ultimately safer measure of trying to block off these routes to trespassers.
4. Response to Paragraph (4)
4.1 The route used by Elliot to access the Facility was to walk across the weir from the bank opposite, climb over the sluice gate structure and over a timber fence. The sluice gates (which are a listed structure) and the weir substantially predate the construction of the Facility.
4.2 The sluice gates and weir are not on land which is owned or controlled by YHL. Since the tragic incident YHL has sought to engage with the relevant parties to consider whether it is feasible to construct an additional barrier on or around these structures where they interface with the Facility. YHL does not have the authority to take action unilaterally in relation to any such works.
4.3 YHL has been part of a working group with WMDC and CRT since before the inquest. YHL commissioned a detailed options report which formed the basis of the final design, agreed by the group, for a barrier at this location. The details of that design have been submitted by WMDC to the local planning authority.
4.4 YHL are supporting WMDC in the procurement process for the steel works while the planning application is being reviewed.
4.5 As WMDC take the lead to see construction through to completion, YHL will continue to input on design and procurement where necessary, as well as facilitating the actual construction.
5. Response to Paragraph (5)
5.1 YHL has taken a number of actions to review and implement measures to deter unauthorised access to the Facility and, should access be gained, to try and minimise the risks that are present. The dynamic environment, the impact of flood water and debris as well as the requirement to facilitate safe operational access makes this site very challenging. YHL has shown that it is committed to continual improvement. In summary since Elliot's tragic death, the key measures that YHL has implemented are: (a) Additional fence returns and mesh infills to deter climbing/access from the land side of the Facility (b) Additional warning signs

Yorkshire Hydropower Limited Company no. 09076541, C/O RES White Limited, Beaufort Court, Egg Farm Lane, Kings Langley, WD4 8LR Yorkshire Hydropower Limited (c) Enhanced CCTV system (with greatly improved coverage and resolution), actively monitored at all times. (d) Improved PA system to enable loud warnings to be issued remotely on detection of trespassers. (e) Various measures to block off routes within the Facility, through the use of barriers and secure gates. (f) Covering of some channels where practicable to do so. (g) Ongoing liaison with the local emergency services. (h) Daily manned security presence during summer months from 10am to 8pm.
5.2 It remains the case that both youths and also adults are accessing the Facility or attempting to do so with little regard for their own safety. We are addressing areas of vulnerability as we become aware of them.
5.3 Whilst traversing across the weir in itself presents significant risk to the individual, we are aware that this remains a key vulnerability in terms of the security of the Facility. It is anticipated that with the progress now being made with the riverside fencing this will soon be addressed. In the interim, we hope that the ongoing manned security presence and remote monitoring will deter further trespass.
6. Summary
6.1 The Facility was designed to be a safe working environment within a secure outer perimeter. To that end a complete security fence was installed to keep trespassers out of the Facility, and guard rails and approved access routes were provided to keep authorised persons within the Facility safe.
6.2 Following the death of Elliot Burton in July 2019 investigations have demonstrated that despite significant and constantly developing measures to prevent unauthorised access some individuals are still determined to access the Facility and are prepared to take on significant risks to their own safety in order to do so.
6.3 This presents numerous challenges due to the location of the Facility and the time it takes to respond to trespass entries, time which the entrants know they have before they are likely to be physically challenged by police or security staff. The site is complex and presents many potential hazards to those prepared to actively bypass passive safety devices. However, normal preventative measures are complicated by the Facility’s location within a flood plain and an active flood zone. This necessitates specific measures to ensure the Facility’s resilience to such flooding and the safety of the maintenance contractors who are responsible for clearing up and repair the Facility following these natural events.
6.4 It is not possible to remove all potential risks from a site such as this and there remains a balance between ensuring the safety of those who make a deliberate attempt to gain unauthorised entry to private property and those who have to legitimately operate and maintain the same Facility. The measures detailed and discussed in this response seek to manage that balance to ensure that the Facility remains safe and operational yet minimise the risks to all people, even those who choose to trespass.

Director for and behalf of Yorkshire Hydropower Limited
Foresight Group
30 Jun 2021
Foresight Group, as an investment advisor to Yorkshire Hydropower Limited (YHL), clarifies that they do not control YHL's affairs but have reviewed and endorse the measures YHL is taking to address site security and safety concerns, including additional fencing, enhanced CCTV, PA system, and manned security presence. AI summary
View full response
Dear Sir Regulation 28 report - Elliot Peter Burton Foresight Group ("Foresight") write in relation to the above Inquest heard on 30 April 2021 following the sad death of Elliot Peter Burton on 29 July 2019. In particular, we seek to address the concerns set out in the Regulation 28 report dated 30 April 2021. We are grateful to you for drawing these concerns to our attention. This was indeed a very tragic event and our thoughts and deepest sympathies go out to Elliot's family and friends. We were not granted Interested Person status and so could not address the Inquest directly but we understand the evidence led to some concerns about:
1. the site location and its site security;
2. historic trespass incidents;
3. the safety measures around the water in the facility;
4. access to the site via the weir across the River Calder; and
5. action to be taken to reduce the risk of harm of trespass by children.

Before turning to these concerns, we wish to set out the factual background which we hope will provide some explanation as the reasons for our response.

Background Foresight is an infrastructure and private equity investment management company with extensive portfolios across a number of funds. In the vast majority of companies in respect of which we advise we appoint a Non-Executive Director, to enhance and protect our client's/the funds' investment. In line with our normal practice was appointed to the board of Yorkshire Hydropower Limited ("YHL") in the role of Non-Executive Director. He was, of course, a witness in relation to the inquest and is a Senior Portfolio Executive employed by our business with extensive experience in renewable energy. In terms of the relationship between Foresight and YHL, we act in our capacity as investment advisors, making business recommendations to our client, which is an institutional investor, and the ultimate owner of YHL since 19 July 2019 (i.e. very shortly before the fatal accident). We do not own or have any financial stake in YHL, nor do we have a direct contractual relationship with the business itself.

The nature of our activities pertaining to YHL YHL operated Kirkthorpe Hydropower Station. We are contracted to provide Investment Advisory Services to the aforementioned institutional investor. Our role includes ensuring and monitoring that there are appropriate contractual relationships and competent advisors in place to support the business, from a financial perspective. This obligation does not, however, include day to day management of YHL or its parent company (YHL Holdings Limited)'s affairs; or advice relating to health and safety matters. Instead, as above, we provide Non-Executive Directors with relevant experience, who fulfil their roles independently and impartially, as they are required to by law. We understand that we were not at any stage suggested to be a party to this Inquest. Foresight's links with YHL at the relevant time derived from its contract with YHL's ultimate parent and the employment of Mr Hardy, both of which are addressed below. As a responsible company, and in light of your concerns raised in the Regulation 28 report, we have reviewed the recordings of the evidence given to identify any steps required on Foresight's part. However we have identified nothing indicating that Foresight had control of YHL's operations, or that role with Foresight dictated or constrained his actions as a director of YHL. Such operational decisions were, and are, decisions for YHL to make, entirely independent of Foresight, as these companies have separate legal personas. Any person holding a director role by virtue of Foresight's Investment Advisory Services contract is an employee of Foresight's business and a director of YHL. Any such individual is fulfilling two distinct roles, which are clearly delineated and do not afford Foresight any control over YHL, including how any director should have exercised their discretion as a director. Clearly any director has a statutory obligation to act only in the best interests of the company and not to vote on matters in which they had a conflict of interest.

Foresight does routinely provide training to Directors, and those who may become Directors, on their duties and expectations in the role of Director on project company boards. This training is provided by third party training providers and covers legal, commercial and operational aspects of Directors' duties. It also includes training on specific duties Directors have in relation to health and safety matters, which is recognised by the Institution of Occupational Health and Safety (IOSH). This training is intended to equip those who may fulfil a statutory role on their obligations so that they can discharge these responsibly. Although we are extremely saddened by Mr Burton's death, we feel obliged to respectfully drawn the factual situation to your attention so as to assuage any concerns over the fact that it is YHL who are taking the steps to ensure there is no repetition of this tragic accident. As set out above, we cannot and do not exercise any control over YHL's affairs. Despite the previous paragraph, Foresight treats this situation with the utmost seriousness and gravity. We have taken up the matter with YHL in order to establish what steps it has taken and proposes to take, in order to be assured that appropriate action has been taken. We have now had the opportunity to review the draft response prepared on behalf of YHL and we fully endorse and support the proposed measures they have outlined in that document. For completeness we note that those actions include: -

(A) Additional fence returns and mesh infills to deter climbing/access from the land side of the Facility (B) Additional warning signs (C) Enhanced CCTV system (with greatly improved coverage and resolution), actively monitored at all times. (D) Improved PA system to enable loud warnings to be issued remotely on detection of trespassers. (E) Various measures to block off routes within the Facility, through the use of barriers and secure gates. (F) Covering of some channels where practicable to do so. (G) Ongoing liaison with the local emergency services. (H) Daily manned security presence during summer months from 10am to 8pm.

We believe that the security of the site will be greatly enhanced by these measures, and by any steps taken by both the Local Authority and the Canal and Rivers Trust.

We do hope that this letter is self-explanatory but would be happy to provide further information if that would be of assistance.
from Canal River Trust
The Canal & River Trust has produced and disseminated a Schools Water Safety Awareness Communication and a water safety video for children aged 5-11, with all primary schools in the Wakefield area receiving multiple emails regarding these resources. AI summary
View full response
Canal & River Trust First Floor North Station House 500 Elder Gate Milton Keynes MK9 1BB W: www.canalrivertrust.org.uk

Page 2
• A Schools Water Safety Awareness Communication produced by the Trust's national Education team.
• A water safety video aimed at children aged 5 –11 years which focuses on the Trust's ‘Stay Away Fr
• All primary schools across Wakefield and surrounding area have received multiple emails as part of bo
Action Should Be Taken
In my opinion action should be taken to prevent future deaths and believe you and your organisations have the power to take such action
Report Sections
Investigation and Inquest
On August 2019, commenced an investigation into the death of Elliot Peter Burton, aged 15. The investigation concluded at the end of the Inquest on 30 April 2021. The conclusion of the Inquest was misadventure due to drowning:
Circumstances of the Death
On Monday 29 2019, Elliot Peter Burton; aged 15, was found drowned on the site of yorkshire Hydropower Limited; known as the Kirkthorpe Hydroelectric Plant; located on the river Calder, near Noranton; West Yorkshire. CCTV records show Elliot had entered the unmanned site as a trespasser on the morning of Thursday 25 July 2019. As he wandered around the site, he slipped and fell into the water at approximately 10.30 am at the section referred to as the outlet channel The smooth tall concrete sides of this enclosure would have prevented him climbing out, He was unable to swim and s0 would probably been unable to reach the escape ladder in the corner of the enclosure, even if he was aware of its position. There was no one on site to him or effect a rescue
Related Inquiry Recommendations

Public inquiry recommendations addressing similar themes

Review CCTV monitoring SIA licence requirements
Manchester Arena Inquiry
Unregulated recreation safety
Enact Protect Duty into law
Manchester Arena Inquiry
Unregulated recreation safety
Establish standard for event healthcare services
Manchester Arena Inquiry
Unregulated recreation safety
Mandatory Ambulance Liaison Officer at events
Manchester Arena Inquiry
Unregulated recreation safety
Employer requirement to train in first aid
Manchester Arena Inquiry
Unregulated recreation safety
Review licensing for security contractors
Manchester Arena Inquiry
Unregulated recreation safety
Replace Buried Metallic LPG Pipes
ICL Inquiry
Public Infrastructure Physical Hazards
New LPG Safety Regime
ICL Inquiry
Public Infrastructure Physical Hazards
LPG Supplier Registration
ICL Inquiry
Public Infrastructure Physical Hazards
Polyethylene Piping Research
ICL Inquiry
Public Infrastructure Physical Hazards

Data sourced from Courts and Tribunals Judiciary under the Open Government Licence.