Crossrail: A progress update
Public Accounts Committee
Closed
Inquiry
Crossrail is a large, complex programme to run a new direct rail line across London, known as the Elizabeth line and part of Transport for London’s rail and underground network. The Elizabeth line is now in its final stages. It became clear in 2018 that the original schedule and cost …
Read more
6
Recommendations
18
Conclusions
1
Report
1
Oral session
3
Letters
1
Event
Activity timeline 6 events
21 Jan
2022
2022
29 Oct
2021
2021
Report published
10 Sep
2021
2021
20 Jul
2021
2021
19 Jul
2021
2021
Oral evidence
Oral evidence sessions 1 session
19 Jul 2021
View on parliament.uk
Crossrail: A progress update
Andy Byford · Transport for London
Bernadette Kelly CB · Department for Transport
Mark Wild · HS2 Ltd
Matt Lodge · Department for Transport
Reports 1 report · click to expand
| Title | HC No. | Published | Items | Response |
|---|---|---|---|---|
| Twenty-Fourth - Crossrail: A progress update | HC 184 | 29 Oct 2021 | 24 | Responded |
Recommendations & Conclusions
10 results
2
Recommendation
Not Addressed
Twenty-Fourth - Crossrail: A progr…
The collapse in passenger numbers owing to the pandemic, and subsequent bailout to TfL, has...
The collapse in passenger numbers owing to the pandemic, and subsequent bailout to TfL, has complicated how and when TfL and the Greater London Authority will be able to repay the taxpayer loans for Crossrail. To date, the taxpayer has …
Read more
Government Response
The government agrees with the committee's general conclusion but does not commit to providing TfL’s revenue forecast scenarios or their implications for Crossrail loan repayment by the requested deadline. Instead, it describes its general value for money assessment processes and commitments for future letters.
HM Treasury
View details
3
Recommendation
Not Addressed
Twenty-Fourth - Crossrail: A progr…
It is not clear to passengers and businesses when the Elizabeth line will open or...
It is not clear to passengers and businesses when the Elizabeth line will open or what services will be available. The Elizabeth line services will open in stages. Services have been running on the eastern and western ends of the …
Read more
Government Response
The government's response discusses managing supplier performance, financial and programme risk, and contract mechanisms, which does not address the recommendation for a clear public communication strategy regarding Elizabeth Line service openings.
HM Treasury
View details
4
Recommendation
Not Addressed
Twenty-Fourth - Crossrail: A progr…
We are concerned that TfL and the Department do not have a plan to maximise...
We are concerned that TfL and the Department do not have a plan to maximise the long-term, wider economic benefits of Crossrail. When open, the Elizabeth line should increase capacity in central London by around 10%, reduce journey times, improve …
Read more
Government Response
The government's response discusses the Ministry of Defence's track record on delivering savings and improving programme delivery, failing entirely to address the recommendation for TfL and the Department to publish a plan for maximising Crossrail's long-term economic benefits.
HM Treasury
View details
1
Conclusion
Not Addressed
Twenty-Fourth - Crossrail: A progr…
On the basis of a report by the Comptroller and Auditor General, we took evidence...
On the basis of a report by the Comptroller and Auditor General, we took evidence from the Department for Transport (the Department), Transport for London (TfL) and Crossrail Ltd on progress with the Crossrail programme.1
Government Response
The government response serves as an introduction to its overall response, providing background on the Crossrail project and the committee's report, rather than directly addressing the conclusion which merely states the committee took evidence.
HM Treasury
View details
6
Conclusion
Not Addressed
Twenty-Fourth - Crossrail: A progr…
A significant software update is needed to begin Trial Operations, which will allow up to...
A significant software update is needed to begin Trial Operations, which will allow up to 24 trains an hour to run through the central section.10 Any unexpected issues with software may take time to fix and we have reported on …
Read more
Government Response
The government response states agreement with the conclusion but then discusses defense spending and equipment plans, which does not address the conclusion regarding Crossrail software updates and trial operations.
HM Treasury
View details
8
Conclusion
Not Addressed
Twenty-Fourth - Crossrail: A progr…
The estimated cost of Crossrail has increased by £1.9 billion since we last reported and...
The estimated cost of Crossrail has increased by £1.9 billion since we last reported and now stands at £18.9 billion.18 This excludes the £1.1 billion cost of the new trains and the depot at Old Oak Common which have historically …
Read more
Government Response
The government's response lists unrelated reports on Greensill Capital and completely fails to address the committee's conclusion regarding Crossrail's cost increases.
HM Treasury
View details
10
Recommendation
Not Addressed
Twenty-Fourth - Crossrail: A progr…
At May 2021, Crossrail Ltd estimated that its cost to complete the programme would be...
At May 2021, Crossrail Ltd estimated that its cost to complete the programme would be between £15,820 million and £16,008 million, with a middle value of £15,910 million. This was between £30 million and £218 million above the current funding …
Read more
Government Response
The government's response provides an update on Crossrail's overall funding status, but it does not address the specific recommendation for Crossrail Ltd to end expensive Tier 1 contracts to control costs.
HM Treasury
View details
13
Conclusion
Not Addressed
Twenty-Fourth - Crossrail: A progr…
TfL told us that it is over-reliant on income through the farebox which accounts for...
TfL told us that it is over-reliant on income through the farebox which accounts for 72% of TfL income. TfL compared this to New York City Transit which received 38% of its income from fares.37 It told us that COVID …
Read more
Government Response
The government's response discusses updated Elizabeth line passenger forecasts and the impact of the COVID-19 pandemic on ridership, but does not address the committee's conclusion about TfL's over-reliance on farebox income or the need to diversify revenue streams.
HM Treasury
View details
18
Conclusion
Not Addressed
Twenty-Fourth - Crossrail: A progr…
The Department and TfL told us that, when the Elizabeth line opens, they expect it...
The Department and TfL told us that, when the Elizabeth line opens, they expect it to increase rail capacity in central London by around 10%, reduce journey times, and be fully accessible.50 These were the transport benefits set out in …
Read more
Government Response
The government's response details its communications strategy regarding the Elizabeth line's opening dates and phases, but does not address the committee's observations about the expected transport and economic benefits.
HM Treasury
View details
19
Conclusion
Twenty-Fourth - Crossrail: A progr…
The Department and Crossrail Ltd told us about the benefits Crossrail has achieved during construction.
The Department and Crossrail Ltd told us about the benefits Crossrail has achieved during construction. Crossrail Ltd told us that Crossrail had “overreached” on its apprenticeship targets, achieving 1,000 apprenticeships. Many of the 1,000 were in civil engineering in the …
Read more
HM Treasury
View details
Government Response AI assessment · 23 of 6 classified
Accepted
3
Acknowledged
11
Total
6 recs + 18 conclusions
Correspondence 3 letters
10 Sep 2021
Correspondence from Bernadette Kelly CB, Permanent Secretary, Transport for London, re Crossrail: A progress update, dated 4 August 2021
Parliament page
20 Jul 2021
Correspondence from Bernadette Kelly CB, Permanent Secretary and Andy Byford Commissioner, TfL, re Crossrail Update, 14 July 2021
Parliament page
29 Jun 2021
Correspondence from Mark Wild, CEO, Crossrail Ltd, re Crossrail progress update: Spring 2021, dated 22 June 2021,
Parliament page