HS2: Update following the Northern leg cancellation
Public Accounts Committee
Closed
Inquiry
In October 2023, the Government announced the cancellation of Phase 2 of the High Speed 2 (HS2) railway from the West Midlands to Manchester, as well as a smaller HS2 station in London Euston. Following this announcement, the Department for Transport (DfT) and DfT’s arm’s-length body HS2 Ltd began work …
Read more
8
Recommendations
43
Conclusions
1
Report
1
Oral session
15
Letters
1
Event
Activity timeline 19 events
4 Sep
2025
2025
9 Jul
2025
2025
8 Jul
2025
2025
3 Jul
2025
2025
30 Jun
2025
2025
26 Jun
2025
2025
9 Jun
2025
2025
19 May
2025
2025
16 May
2025
2025
17 Mar
2025
2025
28 Feb
2025
2025
Report published
Oral evidence sessions 1 session
19 Dec 2024
View on parliament.uk
Alan Foster · HS2 Ltd
Alan Over · Department for Transport
Dame Bernadette Kelly DCB · Department for Transport
Mark Wild · HS2 Ltd
Reports 1 report · click to expand
| Title | HC No. | Published | Items | Response |
|---|---|---|---|---|
| 10th Report - HS2: Update following the Northern leg cancellation | HC 357 | 28 Feb 2025 | 51 | Responded |
Recommendations & Conclusions
4 results
31
Conclusion
Acknowledged
10th Report - HS2: Update followin…
Expanded Euston programme scope includes commercial development, housing, and station redevelopments.
In the October 2023 announcement, the government at the time set out that the HS2 station itself would be planned to be smaller, reflecting the lower number of train services expected to operate following the cancellation of Phase 2. However, …
Read more
Government Response
The government agrees with the committee’s observation and will provide an update on progress concerning the Euston programme in its next six-monthly report to Parliament, expected in Summer 2025.
HM Treasury
View details
32
Conclusion
Acknowledged
10th Report - HS2: Update followin…
Department pursues holistic Euston approach, progressing new delivery company and corporation models.
The Department told us that the new approach to Euston is now a holistic one, seeking to build consensus between stakeholders and as a unified delivery rather than the ineffective attempts of the past to try to solve each part …
Read more
Government Response
The government agrees with the conclusion and will provide an update on progress on Euston in its next six-monthly report to Parliament, expected in Summer 2025.
HM Treasury
View details
34
Conclusion
Acknowledged
10th Report - HS2: Update followin…
Department stresses need for correct financial incentives in new Euston delivery company.
The Department also pointed to the need to get the financial incentives right in the new delivery company, including what the shareholding and financial participation would be between the different bodies, so that people consider the collective interest, not just …
Read more
Government Response
The government agrees with the conclusion and will provide an update on progress on Euston, which implicitly covers aspects of the new delivery company, in its next six-monthly report to Parliament in Summer 2025.
HM Treasury
View details
35
Conclusion
Acknowledged
10th Report - HS2: Update followin…
Department anticipates mixed funding for Euston station, including significant private investment.
We also challenged the Department on the likelihood of obtaining the more than £6 billion that the station at Euston is estimated to cost from the private sector. The Department suggested that the funding for Euston would likely be a …
Read more
Government Response
The government agrees with the conclusion and will provide an update on progress on Euston, including potentially on funding, in its next six-monthly report to Parliament in Summer 2025.
HM Treasury
View details
Correspondence 15 letters
4 Sep 2025
To committee
Letter from the Permanent Secretary of the Department for Transport and High Speed Two Limited Chief Executive relating to the 10th Report of Session 2024-25, HS2: update following the Northern leg cancellation, recommendation 1 and 4, 22 July 2025
Parliament page
9 Jul 2025
To committee
Letter from the Permanent Secretary of the Department of Transport and the Chief Executive of HS2 Ltd relating to Bat mitigation on HS2, 8 July 2025
Parliament page
8 Jul 2025
To committee
Letter from the Permanent Secretary of the Department for Transport and the Chief Executive Officer at HS2 Ltd relating to the recommendations of the Committee's 10th report, HS2: Update following the Northern Leg cancellation, 07 July 2025
Parliament page
3 Jul 2025
From committee
Letter to the Permanent Secretary of the Department for Transport relating to the updated estimate of the HS2 bat mitigation structure at Sheephouse Wood, 03 July 2025
Parliament page
30 Jun 2025
From committee
Letter to the Permanent Secretary of the Department for Transport relating to the Treasury Minute Response on HS2 update following the Northern Leg cancellation, 24 June 2025
Parliament page
26 Jun 2025
To committee
Letter from the Interim Permanent Secretary of the Department for Transport and Chief Executive of High Speed Two Limited relating to the Sheephouse Wood bat mitigation structure, 20 June 2025
Parliament page
9 Jun 2025
From committee
Letter to the Permanent Secretary of the Department for Transport relating to the cost breakdown of the HS2 bat mitigation structure at Sheephouse Wood, 05 June 202
Parliament page
19 May 2025
To committee
Letter from the Permanent Secretary of the Department for Transport relating to the 10th Report of Session 2024-25, HS2: update following the Northern leg cancellation, Recommendation 2, 4, and 8, 15 May 2025
Parliament page
17 Mar 2025
From committee
Letter to the Permanent Secretary of the Department for Transport relating to the HS2 Euston tunnelling schedule, 06 March 2025
Parliament page
4 Feb 2025
To committee
Letter from the Permanent Secretary of the Department for Transport relating to the cost breakdown of the HS2 bat mitigation structure at Sheephouse Wood, 31 January 2025
Parliament page
20 Jan 2025
To committee
Letter from the Permanent Secretary of the Department for Transport relating to a follow up on questions during the oral evidence session held on 19 December 2024, 10 January 2025
Parliament page
20 Jan 2025
To committee
Letter from the Deputy Chief Executive Officer at High Speed Two (HS2) Limited relating to the oral evidence session on 19 December 2024, 10 January 2025
Parliament page
20 Jan 2025
To committee
Letter from the Permanent Secretary of the Department for Transport relating to a follow up on HS2 Resident’s and Construction Commissioner role, 10 January 2025
Parliament page
2 Jan 2025
From committee
Letter to the Permanent Secretary of the Department for Transport relating to the oral evidence session held on 19 December 2024, 23 December 2024
Parliament page
19 Dec 2024
To committee
Letter from the Permanent Secretary of the Department for Transport relating to the publication of the High Speed Two (HS2) Parliamentary Report, 17 December 2024
Parliament page