HS2: Update following the Northern leg cancellation

Public Accounts Committee Closed Inquiry
Opened: 31 Oct 2024 Closed: 16 May 2025 Parliament page
In October 2023, the Government announced the cancellation of Phase 2 of the High Speed 2 (HS2) railway from the West Midlands to Manchester, as well as a smaller HS2 station in London Euston. Following this announcement, the Department for Transport (DfT) and DfT’s arm’s-length body HS2 Ltd began work … Read more
8 Recommendations
43 Conclusions
1 Report
1 Oral session
15 Letters
1 Event
Activity timeline 19 events
Oral evidence sessions 1 session
Alan Foster · HS2 Ltd Alan Over · Department for Transport Dame Bernadette Kelly DCB · Department for Transport Mark Wild · HS2 Ltd
Recommendations & Conclusions
1 result
45 Conclusion Not Addressed
10th Report - HS2: Update followin…
East-west rail connectivity in the North now considered as series of programmes
The Department told us it is also carrying out development work on how to improve the east–west rail connectivity in the north of England. It said that this may well now be considered as a series of programmes and choices … Read more
Government Response
The government provides a boilerplate response focused on land disposal for Phase 2, which does not address the committee's observation regarding east-west rail connectivity in the north of England.
HM Treasury
View details
Government Response AI assessment · 51 of 8 classified

Total 8 recs + 43 conclusions
Correspondence 15 letters
4 Sep 2025 To committee Letter from the Permanent Secretary of the Department for Transport and High Speed Two Limited Chief Executive relating to the 10th Report of Session 2024-25, HS2: update following the Northern leg cancellation, recommendation 1 and 4, 22 July 2025
Parliament page
9 Jul 2025 To committee Letter from the Permanent Secretary of the Department of Transport and the Chief Executive of HS2 Ltd relating to Bat mitigation on HS2, 8 July 2025
Parliament page
8 Jul 2025 To committee Letter from the Permanent Secretary of the Department for Transport and the Chief Executive Officer at HS2 Ltd relating to the recommendations of the Committee's 10th report, HS2: Update following the Northern Leg cancellation, 07 July 2025
Parliament page
3 Jul 2025 From committee Letter to the Permanent Secretary of the Department for Transport relating to the updated estimate of the HS2 bat mitigation structure at Sheephouse Wood, 03 July 2025
Parliament page
30 Jun 2025 From committee Letter to the Permanent Secretary of the Department for Transport relating to the Treasury Minute Response on HS2 update following the Northern Leg cancellation, 24 June 2025
Parliament page
26 Jun 2025 To committee Letter from the Interim Permanent Secretary of the Department for Transport and Chief Executive of High Speed Two Limited relating to the Sheephouse Wood bat mitigation structure, 20 June 2025
Parliament page
9 Jun 2025 From committee Letter to the Permanent Secretary of the Department for Transport relating to the cost breakdown of the HS2 bat mitigation structure at Sheephouse Wood, 05 June 202
Parliament page
19 May 2025 To committee Letter from the Permanent Secretary of the Department for Transport relating to the 10th Report of Session 2024-25, HS2: update following the Northern leg cancellation, Recommendation 2, 4, and 8, 15 May 2025
Parliament page
17 Mar 2025 From committee Letter to the Permanent Secretary of the Department for Transport relating to the HS2 Euston tunnelling schedule, 06 March 2025
Parliament page
4 Feb 2025 To committee Letter from the Permanent Secretary of the Department for Transport relating to the cost breakdown of the HS2 bat mitigation structure at Sheephouse Wood, 31 January 2025
Parliament page
20 Jan 2025 To committee Letter from the Permanent Secretary of the Department for Transport relating to a follow up on questions during the oral evidence session held on 19 December 2024, 10 January 2025
Parliament page
20 Jan 2025 To committee Letter from the Deputy Chief Executive Officer at High Speed Two (HS2) Limited relating to the oral evidence session on 19 December 2024, 10 January 2025
Parliament page
20 Jan 2025 To committee Letter from the Permanent Secretary of the Department for Transport relating to a follow up on HS2 Resident’s and Construction Commissioner role, 10 January 2025
Parliament page
2 Jan 2025 From committee Letter to the Permanent Secretary of the Department for Transport relating to the oral evidence session held on 19 December 2024, 23 December 2024
Parliament page
19 Dec 2024 To committee Letter from the Permanent Secretary of the Department for Transport relating to the publication of the High Speed Two (HS2) Parliamentary Report, 17 December 2024
Parliament page