Decommissioning Sellafield

Public Accounts Committee Closed Inquiry
Opened: 31 Oct 2024 Closed: 21 Aug 2025 Parliament page
The Sellafield nuclear site closed in 2003, having operated since 1950. Work began to decommission the site in 2005. Highly hazardous materials are stored there from across the UK’s nuclear industry, and it holds a legacy of contaminated buildings, untreated waste and ageing facilities. The Nuclear Decommissioning Authority (NDA), the … Read more
9 Recommendations
23 Conclusions
1 Report
1 Oral session
7 Letters
1 Event
Activity timeline 11 events
20 Mar
2025
20 Mar
2025
Formal meeting (oral evidence session) · The Grimond Room, Portcullis House
Oral evidence sessions 1 session
Clive Maxwell · Department for Energy Security and Net Zero David Peattie · Nuclear Decommissioning Authority Euan Hutton · Sellafield Ltd Kate Bowyer · Nuclear Decommissioning Authority Lee McDonough · Department for Energy Security and Net Zero
Recommendations & Conclusions
2 results
14 Conclusion Acknowledged
28th Report - Decommissioning Sell…
Recent major project delivery at Sellafield shows tangible signs of improvement, with several projects on track.
DESNZ told us that it nevertheless believes that “there is some tangible evidence on improvement” and that “the overall direction of travel on project delivery is improving at the site”.36 Four of the five major projects which have been approved … Read more
Government Response
The government acknowledges the positive progress in major project delivery at Sellafield, referencing the NAO report and the positive contributions of the Programme and Project Partners (PPP) model.
HM Treasury
View details
15 Conclusion Acknowledged
28th Report - Decommissioning Sell…
New Programme and Project Partners (PPP) model improves major project delivery at Sellafield.
We asked the witnesses to explain what has led to the apparent improvement in how projects are now being delivered. Sellafield Ltd told us that it was now delivering its largest projects in a new way, which it calls ‘Programme … Read more
Government Response
The government acknowledges the positive progress in major project delivery at Sellafield, referencing the NAO report and the positive contributions of the Programme and Project Partners (PPP) model.
HM Treasury
View details
Government Response AI assessment · 31 of 9 classified

Total 9 recs + 23 conclusions
Correspondence 7 letters
8 Jan 2026 To committee Letter from the Interim Permanent Secretary at the Department for Energy Security & Net Zero relating to Decommissioning Sellafield, 12 December 2025
Parliament page
8 Jan 2026 To committee Letter from the Group Chief Executive of the Nuclear Decommissioning Authority relating to Decommissioning Sellafield, 12 December 2025
Parliament page
15 Dec 2025 To committee Letter from the Chief Executive Officer of Sellafield Ltd relating to recommendations of the Committee’s Twenty-eighth Report on Decommissioning Sellafield, 04 December 2025
Parliament page
24 Nov 2025 To committee Letter from the Chair to the Permanent Secretary at the Department for Energy Security and Net Zero, the Group Chief Executive Officer at the Nuclear Decommissioning Authority and the Chief Executive Officer at Sellafield Ltd relating to Treasury Minute response – Decommissioning Sellafield, 14 November 2025
Parliament page
4 Sep 2025 To committee Letter from the Chief Executive Officer at Sellafield Limited relating to the 28th Report of Session 2024-25, Decommissioning Sellafield, Recommendation 4, 13 August 2025
Parliament page
24 Apr 2025 To committee Letter from the Group Chief Executive Officer at the Nuclear Decommissioning Authority relating to the oral evidence session held on 20 March on Decommissioning Sellafield, 04 April 2025
Parliament page
7 Apr 2025 To committee Letter from the Group Chief Executive Officer of the Nuclear Decommissioning Authority relating to Public Accounts Committee’s visit to Sellafield, March 17
Parliament page