We asked why the Department is forecasting to spend more than its capital budget in...
Recommendation
We asked why the Department is forecasting to spend more than its capital budget in seven of the next 10 years. The Department responded that the differences in those years were quite small and it judged them to be manageable.32 It had taken a conscious decision not to fully “address that pressure”, in order to balance financial and capability risk, given available contingency and the remaining uncertainties in costings and delivery schedules.33 Cost control of the Plan’s largest programmes
Government Response Summary
The government agrees with the recommendation and commits to including an additional section in future Equipment Plans by Autumn 2022, explaining changes and plans made to address emerging developments and the impact of the conflict in Ukraine.
Government Response
Accepted
Government Response
Accepted
HM Government
Accepted
1.1 The department agrees with the Committee’s recommendation. Target implementation date: Autumn 2022 1.2 The Ministry of Defence (the department) recognises the potential impact the conflict in Ukraine has had for future thinking on equipment spending and procurement and this is being examined. The department remains confident that the Equipment Plan 2021-2031 (EP21) retains relevance despite emerging and unpredicted threats and was produced in line with aims and priorities outlined in the Integrated Review. 1.3 The Equipment Plan has to balance competing priorities, but, it is the department’s view that the EP21 successfully addressed and rectified a previous deficit, whilst ensuring increased investment in new capabilities and research or development. The Plan therefore balances short term need and long term aims to ensure it is remains resilient to emerging threats. 1.4 Future Equipment Plans will include an additional section explaining changes made and planned to address emerging developments.
Source
Committee
Public Accounts Committee
Inquiry
MoD Equipment Plan 2021-31
Report
Fifty-Second Report - Ministry of Defence Equipment Plan 2021–31
11 May 2022
HC 1164
Addressee Bodies
HM Treasury
Timeline
Recommendation age
4.2 yrs
Report published
11 May 2022