Conclusion
We are concerned that this partnership-based system is not clear on responsibilities and may not be robust enough for difficult trade-off decisions between local areas.48 For example, an underground station at Manchester Piccadilly would enable more development opportunities above the station than alternatives at surface level, but is expected to be more costly and could therefore reduce the budget available for additional development in other localities.49
Source
Committee
Public Accounts Committee
Inquiry
Northern Powerhouse Rail
Report
8th Report - Northern Powerhouse Rail
01 Jul 2026
HC 97
Addressee Bodies
HM Treasury
Timeline
Recommendation age
0.1 yrs
Report published
01 Jul 2026