Thirty-Second Report - Delivering gigabitcapable broadband

Select Committee
Public Accounts Committee HC 743 19 January 2022
Report Status Government responded
Conclusions & Recommendations 27 items (5 recs)
Government Response (AI assessment · 27 of 27 classified)
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Thirty Second report from Session 2021-22 · published 28 Apr 2022

Recommendations & Conclusions

8 results
8 Conclusion Acknowledged
In changing its target, it has also made changes to the type of technology it...
Conclusion
In changing its target, it has also made changes to the type of technology it plans to use to achieve gigabit broadband rollout.19 In 2019, the Department revised its target from full fibre to “gigabit-capable” broadband. Some stakeholders considered this … Read more
Government Response Summary
The government highlights the UK's progress in gigabit connectivity, the number of companies involved, and the coverage achieved to date, attributing it to clear targets and a competitive regulatory environment.
HM Treasury
View Details
9 Conclusion Acknowledged
In its letter to us ahead of our evidence session, the Department told us that...
Conclusion
In its letter to us ahead of our evidence session, the Department told us that there had been a rapid increase in nationwide gigabit coverage to 57% coverage in October 2021, up from 34% in November 2020.23 However, the most … Read more
Government Response Summary
The government provides updated statistics on gigabit and full fibre coverage as of March 2022, attributing contributions to Virgin Media O2, Openreach, and alternative network providers.
HM Treasury
View Details
10 Conclusion Acknowledged
The Department expects commercial operators will supply broadband infrastructure where profitable, and that this will...
Conclusion
The Department expects commercial operators will supply broadband infrastructure where profitable, and that this will provide up to 80% of the UK’s coverage.27 To achieve the additional coverage needed to meet its 85% target, the Department plans to provide subsidies … Read more
Government Response Summary
The Department expects commercial operators will supply broadband infrastructure where profitable and is working with these operators to provide subsidies to build gigabit infrastructure in less commercially viable areas and is providing funding through the gigabit voucher scheme as immediate help for people experiencing slow broadband speeds in rural areas.
HM Treasury
View Details
11 Conclusion Acknowledged
The Department has yet to sign the gigabit infrastructure contracts with commercial suppliers under which...
Conclusion
The Department has yet to sign the gigabit infrastructure contracts with commercial suppliers under which it would provide public subsidy for them to build in areas that would otherwise not get coverage as they are less commercially viable.31 The dates … Read more
Government Response Summary
BDUK reported launching its first six procurements for up to 187,400 premises and provided its procurement pipeline for up to 2.3 million more premises to be included in contracts awarded by the end of 2024.
HM Treasury
View Details
13 Conclusion Acknowledged
We asked the Department about concerns among some of our constituents who are feeling increasingly...
Conclusion
We asked the Department about concerns among some of our constituents who are feeling increasingly left behind as a result of private sector roll-out to the more commercially viable parts of constituencies. We asked it why its planning was slipping … Read more
Government Response Summary
BDUK balances the need to be dynamic and responsive to the market’s plans while maintaining a minimum level of certainty that suppliers will build viable networks to uncommercial areas and consequently ensure appropriate value for money.
HM Treasury
View Details
15 Conclusion Acknowledged
The Department’s answers during our more recent evidence session suggested that it is still not...
Conclusion
The Department’s answers during our more recent evidence session suggested that it is still not making progress at pace in tackling barriers to gigabit roll out. For example, the Telecommunications Infrastructure (Leasehold Property) Act 2021 (TILPA) received Royal Assent on … Read more
Government Response Summary
The department has introduced the Product Security and Telecommunications Infrastructure Bill, worked with DfT and industry to implement and trial further reforms to streetworks and permitting, published a statutory technical consultation on ‘new build’ home gigabit-capable connectivity, introduced changes to permitted development rights, and taken steps to make it easier and quicker to deploy mobile equipment on local authority buildings and street furniture.
HM Treasury
View Details
23 Conclusion Acknowledged
In our January 2021 report, we found that the most difficult to reach areas were...
Conclusion
In our January 2021 report, we found that the most difficult to reach areas were not neatly grouped together, and the Department was not yet clear how it would prioritise its interventions to ensure that they are served. As the … Read more
Government Response Summary
BDUK will publish its profile to reach at least 5% of non-commercial premises by the end of 2025 in its 2022-23 corporate plan and will continue to publish quarterly updates on its pipeline of Gigabit Infrastructure Subsidy contracts. A call for evidence was made to explore all possible options for improving broadband connectivity for these Very Hard to Reach premises, and the government published its response in February 2022.
HM Treasury
View Details
24 Conclusion Acknowledged
The Department asserted that where there are variations found within urban areas, those pockets which...
Conclusion
The Department asserted that where there are variations found within urban areas, those pockets which are currently unviable are expected to be covered by commercial operators over the course of the next few years. However, should that not be the … Read more
Government Response Summary
In March 2021, a call for evidence was made to explore all possible options for improving broadband connectivity for Very Hard to Reach premises, and the government published its response in February 2022. This evidence will be used to assess policy options to understand how best to address the small minority of premises that will be beyond the scope of the programme, and the department will publish further details later this year.