Twenty-Second - Improving the performance of major defence equipment contracts
Select Committee
Public Accounts Committee
HC 185
3 November 2021
Government Response (AI assessment · 21 of 24 classified)
Accepted
14
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Twenty Second report from Session 2021-22 · published 21 Jan 2022
Recommendations & Conclusions
1 results
15
Conclusion
Acknowledged
Problems with supplier performance include their inability to undertake complex design work within agreed timetables,...
Conclusion
Problems with supplier performance include their inability to undertake complex design work within agreed timetables, difficulties in satisfying safety regulators’ requirements, and their inability to project management effectively due to under- resourcing.37 However, the Department has also contributed to problems, …
Read more
Government Response Summary
The government recognizes challenges with equipment delivery and states it has existing governance and measures in place to ensure contractor obligations. It commits to writing to the Committee by May 2022 with evidence on how it holds suppliers accountable and apportions risk, but does not specifically address the department's own poor management of integration or GFA delivery.