Direct control room to incident commander communications
The LFB develop a communication system to enable direct communication between the control room and the incident commander and improve the means of communication between the incident commander and the bridgehead.
How was this assessed?
Response
Accepted
Response
AcceptedThe government accepted in principle all the Phase 1 recommendations directed at central government. The Housing Secretary Robert Jenrick presented the formal response to Parliament on 21 January 2020, committing to swift and decisive action including new duties on building owners and managers to provide information to fire and rescue services, install premises information boxes, conduct regular inspections of lifts and fire doors, and equip buildings with evacuation signal facilities. The government stated it had already taken action in advance of the report and was actively looking beyond the remit of these recommendations.
Progress Timeline
The LFB has reported that this recommendation has been completed. The LFB developed a Fire Survival Guidance application (live March 2022) displaying information simultaneously to all staff handling an incident.
LFB Commissioner Andy Roe announced LFB is "the only organisation to have completed every recommendation directed specifically to them." Key achievements: revised FSG policy, new MSA breathing apparatus with voice comms, 64m turntable ladders, fire escape hoods saving 200+ lives.
We accept the recommendations in both the Phase 1 Grenfell Report and HMICFRS inspection report.