Managing the expiry of PFI contracts

Public Accounts Committee Closed Inquiry
Opened: 21 Dec 2020 Closed: 17 May 2021 Parliament page
Private finance initiative (PFI) contracts are a form of public private partnerships used in the UK since the 1990s. PFI is a way to finance and provide public sector infrastructure and capital equipment projects, such as roads, hospitals, and schools. PFI contracts set out a long-term agreement between the private … Read more
12 Recommendations
13 Conclusions
1 Report
1 Oral session
3 Letters
1 Event
Oral evidence sessions 1 session
Managing the expiry of PFI contracts
Charles Roxbourgh · HM Treasury Matthew Vickerstaff · NISTA Sean Hansen · Local Government Association
Recommendations & Conclusions
1 result
1 Conclusion Deferred
Fifty-First Report - Managing the …
What support will be made available, including how additional funding will be provided to authorities...
What support will be made available, including how additional funding will be provided to authorities with limited resources or those with the most challenging contracts. Managing the expiry of PFI contracts 7
Government Response
The government agrees and will write to the Committee, but defers decisions on any additional funding for authorities to the forthcoming 2021 Spending Review.
HM Treasury
View details
Government Response AI assessment · 25 of 12 classified

Total 12 recs + 13 conclusions
Correspondence 3 letters
10 Sep 2021 Correspondence from Matthew Vickerstaff, Deputy CEO, Infrastructure and Projects Authority, re Private Finance Initiative (PFI) Contracts, dated 16 August 2021
Parliament page
8 Mar 2021 Correspondence from Charles Roxburgh Second Permanent Secretary, HM Treasury, re Private Finance Initiative (PFI) contracts, dated 3 March 2021
Parliament page
23 Feb 2021 Correspondence from Sean Hanson, Chief Executive, Local Partnerships, re Managing the expiry of Private Finance Initiative (PFI) contracts, dated 16 February 2021
Parliament page