67th Report - NS&I’s transformation programme

Select Committee
Public Accounts Committee HC 1237 13 February 2026
Report Status Government responded
Conclusions & Recommendations 29 items (7 recs)
Government Response (AI assessment · 29 of 29 classified)
Government response
Treasury minutes: Government response to the Committee of Public Accounts on the Sixty-seventh report from Session 2024-26 · published 7 Apr 2026

Recommendations & Conclusions

1 results
7 Conclusion Not Addressed
NS&I attempted an overly complex, risky programme with too many parallel transitions.
Conclusion
We asked NS&I why it had been trying to do such a complex Programme, splitting operations undertaken by a single supplier into a multi-supplier model, in such a risky way. The NAO report shows that NS&I original planned expected four … Read more
Government Response Summary
The government's response completely fails to address the committee's conclusion about NS&I's complex programme transition and the need for re-evaluation, instead discussing unrelated matters concerning Carer's Allowance overpayments and reassessments.
HM Treasury
View Details