Grenfell Tower Inquiry

Completed
Chair Sir Martin Moore-Bick Judge / Judiciary
Established 15 Aug 2017
Final Report 04 Sep 2024
Commissioned by Cabinet Office Commissioned by the Prime Minister

Public inquiry into the fire at Grenfell Tower on 14 June 2017, which killed 72 people. The inquiry examined the circumstances leading up to and surrounding the fire.

Evidence & Impact
The Grenfell Tower Inquiry was established following the fire on 14 June 2017 that claimed 72 lives. Chaired by Sir Martin Moore-Bick, it examined the circumstances leading to the disaster and made 104 recommendations across two phases, with the final report published in September 2024.

The government accepted 88 recommendations fully and 10 in principle, with only 6 partially accepted. The response demonstrates commitment to reform, though implementation progress varies significantly. Of the 104 recommendations, 54 (52%) are marked as completed, while 50 (48%) remain in progress.

Notable achievements include the Fire Safety Act 2021 and accompanying regulations, which fundamentally reformed fire safety duties for building owners. The establishment of the Building Safety Regulator as an independent body represents significant institutional reform. Fire services have implemented operational changes, with London Fire Brigade revising policies and all services improving control room procedures.

However, substantial work remains incomplete two years after the report. Critical gaps include the absence of mandatory retrofitting for evacuation systems in existing buildings and the limitation of Personal Emergency Evacuation Plans to high-rise buildings only. The construction products reform, identified as essential to preventing future tragedies, remains in consultation phase with a White Paper expected in Spring 2026.

The pattern emerging shows swift action on regulatory changes within existing frameworks but slower progress on reforms requiring new legislation or fundamental restructuring. The fire engineering profession lacks statutory recognition, the proposed College of Fire and Rescue awaits primary legislation, and the comprehensive review of building guidance continues without firm completion dates.

While the high acceptance rate and completed operational changes demonstrate commitment, the number of amber-rated recommendations suggests implementation challenges. The government's approach appears measured but risks losing momentum on complex structural reforms that may prove most critical to preventing future tragedies.
Reforms Attributed to This Inquiry
- Fire Safety Act 2021 commenced in full on 16 May 2022, extending fire safety duties to building structure and external walls
- Fire Safety (England) Regulations 2022 introduced new requirements for building owners including premises information boxes, fire door inspections, and information sharing with fire services
- Building Safety Regulator established as new arms-length body, taking over building safety functions from HSE
- Fire Safety (Residential Evacuation Plans) (England) Regulations 2025 laid before Parliament, mandating Personal Emergency Evacuation Plans in high-rise buildings from April 2026
- London Fire Brigade revised fire survival guidance policies and implemented dedicated communication links between control rooms and incident commanders
- All fire and rescue services implemented policies distinguishing between fire survival guidance and general fire safety advice
- Mandatory competence testing for RIBA Chartered Members acting as designers introduced in 2025
- Interim Chief Construction Adviser appointed September 2025 to monitor building regulations and guide industry reform
- National operational guidance for fire services updated regarding communications loss, water supply systems, and crew briefing procedures
- Updated London Local Authority Gold Operating procedures circulated with new regional training programme commenced
Unfinished Business
- Retrofitting of evacuation alert systems in existing high-rise buildings not mandated, only required in new buildings over 18 metres
- Personal Emergency Evacuation Plans only mandated for high-rise and higher-risk buildings, not all buildings where residents may need them
- Building Safety Regulator not undertaking product testing or certification functions as recommended
- Construction products reform still in development with White Paper expected Spring 2026
- Fire engineering profession regulation framework still being developed with no timeline for statutory recognition
- Principal contractor licensing scheme still under consideration with no implementation date
- Independent Building Control Panel recommendations on national authority for building control pending
- Materials and products information library not yet established
- Fire risk assessor mandatory accreditation system consultation not launched, expected early 2026
- College of Fire and Rescue consultation scheduled for May 2026, requiring primary legislation
- Comprehensive review of Approved Document B ongoing with recommendations expected 2026
- Local authority emergency response guidance for displaced persons still under development
- National resilience standards and intervention powers review still in policy development stage
Generated 10 Mar 2026 using AI. Assessment is indicative, not authoritative.
Influence & Connections
Influenced by Summerland Fire Inquiry
The Summerland fire of 1973 demonstrated that combustible cladding materials can enable rapid and catastrophic fire spread. The same lesson was tragically repeated at Grenfell Tower 44 years later.
Influenced by Ronan Point Inquiry
Ronan Point introduced the concept of resistance to disproportionate collapse in building regulations. The Grenfell Tower fire raised the same fundamental question about the gap between building regulation and safety in practice.
7 years Duration
£177.6m Total Cost
300 Hearing Days
608 Core Participants
1,600 Statements
300,000 Documents
1,700 Report Pages
Government Response

Total Recommendations 104
Data last updated: 25 Feb 2026 · Source
Data verified: 23 Mar 2026 (import)
How to read this

Government Response tracks what the government said it would do (accepted, rejected, etc.).

Full methodology

11 debates 122 questions 20 statements since Jun 2017
Written Ministerial Statement Grenfell Tower Inquiry Recommendations – Progress
Baroness Taylor of Stevenage (Labour)
17 Dec 2025
Written Ministerial Statement Grenfell Tower Inquiry Recommendations – Progress
Samantha Dixon (Labour)
17 Dec 2025
Written Question Fire and Rescue Services: Standards
Victoria Collins (Liberal Democrat)
11 Nov 2025
Written Ministerial Statement Update on the Building Safety Regulator
Samantha Dixon (Labour)
11 Nov 2025
Written Ministerial Statement Update on the Building Safety Regulator
Baroness Taylor of Stevenage (Labour)
11 Nov 2025
View all 161 mentions →
Title Volume Publication Date Recs Links
Grenfell Tower Inquiry: Phase 1 Report Phase 1 30 Oct 2019 46
Grenfell Tower Inquiry: Phase 2 Report Phase 2 04 Sep 2024 58
14 Jun 2017
Grenfell Tower Fire

Fire at Grenfell Tower in North Kensington killed 72 people.

15 Jun 2017
Inquiry Announced

Prime Minister Theresa May announced a public inquiry.

29 Jun 2017
Chair Appointed

Sir Martin Moore-Bick appointed as Chair.

15 Aug 2017
Terms of Reference Set

Terms of Reference published.

Source
14 Sep 2017
Procedural Hearing

First procedural hearing held.

21 May 2018
Phase 1 Hearings Begin

Phase 1 hearings commenced, examining events of the night of the fire.

30 Oct 2019
Phase 1 Report Published

Phase 1 report published with findings on the night of the fire.

Source
27 Jan 2020
Phase 2 Hearings Begin

Phase 2 hearings commenced, examining causes of the fire.

10 Nov 2022
Phase 2 Hearings Conclude

Final Phase 2 evidence hearings concluded.

04 Sep 2024
Phase 2 Report Published

Final report published with 58 recommendations.

Source
04 Sep 2024
Government Response

Prime Minister apologised on behalf of the state.

Source
Total Inquiry Cost (Cumulative) £177,639,000
Cost Breakdown (to Jan 2025)
Inquiry Legal Costs £30,408,000 Panel remuneration & Counsel to the Inquiry
Core Participant Legal Costs £68,888,000 Legal funding for core participants
Staff £40,670,000
Technology £23,985,000
Other £13,688,000
Total inquiry costs Aug 2017 - Jan 2025. Inquiry Legal = Chairman (Sir Martin Moore-Bick), Panel and Counsel. Staff = Secretariat, Accommodation and Operations. Technology = Hearing Room and Legal Tech. Other = Assessors and Expert Witnesses. 619 core participants (585 BSR) funded through 24 solicitors firms and 59 counsel.
Cost History
Period Total Inquiry Legal CP Legal Source
Jan 2025 (cum.) £177,639,000 £30,408,000 £68,888,000
Jan 2025 £4,426,000 £800,000 £1,017,000
Mar 2024 £3,245,000 £1,444,000 -
Mar 2023 £20,698,000 £4,815,000 £8,318,000
Mar 2022 £31,939,000 £6,604,000 £11,299,000
Mar 2021 £77,064,000 £11,615,000 £31,152,000
Mar 2019 £40,267,000 £5,130,000 £18,887,000

Recommendations (104)

P1-1
Accepted
Require external wall information for fire services
Recommendation
The owner and manager of every high-rise residential building be required by law to provide their local fire and rescue service with information about the design of its external walls together with details of the materials of which they are … Read more
Published evidence summary
According to gov.uk (Feb 2025), the Fire Safety Act 2021, which commenced in full on 16 May 2022, and the Fire Safety (England) Regulations 2022, in force since 23 January 2023, legally require responsible persons to provide local fire and rescue services with electronic records of external wall design and materials. This includes informing services of any material changes made to them. According to the government's formal response in January 2020, this recommendation was accepted in principle, committing to new duties on building owners and managers.
UK Government (Primary)
View Details
P1-2
Accepted
Train fire personnel on external wall fire risks
Recommendation

All fire and rescue services ensure that their personnel at all levels understand the risk of fire taking hold in the external walls of high-rise buildings and know how to recognise it when it occurs.

Published evidence summary
According to gov.uk (Feb 2025), all 43 fire and rescue services have trained their personnel at all levels on the risk of fire taking hold in the external walls of high-rise buildings and how to recognise it. This training utilised National Fire Chiefs Council (NFCC) products, covering hazards associated with external wall system failures, including ACM cladding. The NFCC had committed to developing national guidance and training products for all fire and rescue services in England following its acceptance of the Phase 1 recommendations in January 2020.
National Fire Chiefs Council (Primary)
View Details
P1-3
Accepted
LFB to review PN633 Appendix 1
Recommendation

The LFB review, and revise as appropriate, Appendix 1 to PN633 to ensure that it fully reflects the principles in GRA 3.2.

Published evidence summary
According to gov.uk (26 February 2025), the London Fire Brigade (LFB) incorporated guidance from PN 633 into its Management of Operational Risk Information policy (number 800) and completed mandatory training for all operational staff. LFB Commissioner Andy Roe announced in March 2024 that the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P1-4
Accepted
Train LFB officers on high-rise inspections
Recommendation

The LFB ensure that all officers of the rank of Crew Manager and above are trained in carrying out the requirements of PN633 relating to the inspection of high-rise buildings.

Published evidence summary
According to the London Fire Brigade (LFB), all operational staff have completed mandatory training on the revised Management of Operational Risk Information policy (Number 800), addressing the requirement for officers to be trained in high-rise building inspections. According to LFB Commissioner Andy Roe in March 2024, the LFB had completed all recommendations directed specifically to them. According to the LFB, this action aligns with LFB's acceptance of the recommendation in January 2020.
London Fire Brigade (Primary)
View Details
P1-5
Accepted
Require building floor plans for fire services
Recommendation
The owner and manager of every high-rise residential building be required by law to provide their local fire and rescue services with up-to-date plans in both paper and electronic form of every floor of the building identifying the location of … Read more
Published evidence summary
According to reports, the Fire Safety (England) Regulations 2022, which came into force on 23 January 2023, established a legal requirement for responsible persons of high-rise residential buildings to prepare up-to-date floor plans and send them electronically to their local fire and rescue service. This action followed the government's acceptance of the recommendation in principle in January 2020 and its commitment to new duties through the Fire Safety Bill and Building Safety Bill.
UK Government (Primary)
View Details
P1-6
Accepted
Require premises information boxes
Recommendation
The owner and manager of every high-rise residential building be required by law to ensure that the building contains a premises information box, the contents of which must include a copy of the up-to-date floor plans and information about the … Read more
Published evidence summary
According to the Fire Safety (England) Regulations 2022, there is a legal requirement for responsible persons to install a secure premises information box in high-rise residential buildings, containing hard copies of floor plans and information about lifts for fire and rescue services. Additionally, Approved Document B was amended to require secure information boxes in all new residential buildings over 11 metres. These actions followed the government's acceptance of the recommendation in principle in January 2020.
UK Government (Primary)
View Details
P1-7
Accepted
Equip fire services to receive electronic plans
Recommendation

All fire and rescue services be equipped to receive and store electronic plans and to make them available to incident commanders and control room managers.

Published evidence summary
According to the available evidence, all fire and rescue services across England have reported being equipped to receive and store electronic plans, which can be made available to incident commanders and control room managers. According to the National Fire Chiefs Council (NFCC), the completion of this recommendation for all services was confirmed in an October 2023 survey. According to the available evidence, for the London Fire Brigade, this capability is incorporated into its One Risk solution.
National Fire Chiefs Council (Primary)
View Details
P1-8
Accepted
Require monthly firefighter lift inspections
Recommendation
The owner and manager of every high-rise residential building be required by law to carry out regular inspections of any lifts that are designed to be used by firefighters in an emergency and to report the results of such inspections … Read more
Published evidence summary
According to the Fire Safety (England) Regulations 2022, which came into force on 23 January 2023, there is a legal requirement for responsible persons of high-rise residential buildings to undertake monthly checks of lifts designed for use by firefighters and to report any faults electronically to their local fire and rescue service. This action followed the government's acceptance of the recommendation in principle in January 2020 and its commitment to new duties through the Fire Safety Bill and Building Safety Bill.
UK Government (Primary)
View Details
P1-9
Accepted
Require monthly lift control mechanism tests
Recommendation
The owner and manager of every high-rise residential building be required by law to carry out regular tests of the mechanism which allows firefighters to take control of the lifts and to inform their local fire and rescue service at … Read more
Published evidence summary
According to the Gov.uk progress update (26 Feb 2025), monthly testing of lift control mechanisms in high-rise residential buildings became a legal requirement on 23 January 2023, with results reported electronically to fire and rescue services. This requirement was established through the Fire Safety (England) Regulations 2022.
UK Government (Primary)
View Details
P1-10
Accepted
LFB review control room communications policy
Recommendation

The London Fire Brigade review its policies on communications between the control room and the incident commander.

Published evidence summary
According to gov.uk (Feb 2025), the London Fire Brigade (LFB) revised its Policy Number 790 (Fire Survival Guidance), which was published on 31 March 2021, enhancing the gathering, recording, and transfer of Fire Survival Guidance information between the incident ground and the control room. According to LFB Commissioner Andy Roe in March 2024, the LFB had completed all recommendations directed specifically to the organisation. According to HM Inspectorate of Constabulary and Fire & Rescue Services in November 2024, LFB was rated as 'outstanding' for responding to major and multi-agency incidents, noting significant improvements since January 2022.
London Fire Brigade (Primary)
View Details
P1-11
Accepted
Train incident commanders on control room communications
Recommendation

All officers who may be expected to act as incident commanders (i.e. all those above the rank of Crew Manager) receive training directed to the specific requirements of communication with the control room.

Published evidence summary
According to gov.uk (Feb 2025), the London Fire Brigade (LFB) has delivered training to all officers of Crew Manager rank and above, focusing on the specific requirements of communication with the control room. LFB Commissioner Andy Roe announced in March 2024 that the LFB had completed all recommendations directed specifically to the organisation. HM Inspectorate of Constabulary and Fire & Rescue Services rated LFB as 'outstanding' for responding to major and multi-agency incidents in November 2024, noting significant improvements since January 2022.
London Fire Brigade (Primary)
View Details
P1-12
Accepted
Train control room operators on incident commander communications
Recommendation

All control room operators of Assistant Operations Manager rank and above receive training directed to the specific requirements of communication with the incident commander.

Published evidence summary
According to gov.uk (Feb 2025), the London Fire Brigade (LFB) has provided training to all control room operators of Assistant Operations Manager rank and above, specifically on communications with incident commanders. According to LFB Commissioner Andy Roe's statement in March 2024, the LFB had completed all recommendations directed to it. HM Inspectorate of Constabulary and Fire & Rescue Services rated LFB as 'outstanding' for responding to major and multi-agency incidents in November 2024, noting significant improvements since January 2022.
London Fire Brigade (Primary)
View Details
P1-13
Accepted
Dedicated control room to incident commander link
Recommendation

A dedicated communication link be provided between the senior officer in the control room and the incident commander.

Published evidence summary
According to gov.uk (Feb 2025), the London Fire Brigade (LFB) has established a dedicated communication link between the senior officer in the control room and the incident commander. According to LFB Commissioner Andy Roe's confirmation in March 2024, the LFB had completed all recommendations specifically directed to the organisation. HM Inspectorate of Constabulary and Fire & Rescue Services rated LFB as 'outstanding' for responding to major and multi-agency incidents in November 2024, noting significant improvements since January 2022.
London Fire Brigade (Primary)
View Details
P1-14
Accepted
Distinguish between advice and rescue callers
Recommendation

The LFB's policies be amended to draw a clearer distinction between callers seeking advice and callers who believe they are trapped and need rescuing.

Published evidence summary
According to gov.uk (Feb 2025), all fire and rescue services have developed policies that distinguish between callers seeking advice and those who believe they are trapped and require rescue. According to the available evidence, relevant staff across these services have also received training on these distinctions, and according to LFB Commissioner Andy Roe, in March 2024, the LFB had completed all recommendations directed to it, while HM Inspectorate of Constabulary and Fire & Rescue Services rated LFB as 'outstanding' for responding to major and multi-agency incidents in November 2024, noting significant improvements since January 2022.
London Fire Brigade (Primary)
View Details
P1-15
Accepted
Regular refresher training for control room operators
Recommendation

The LFB provide regular and more effective refresher training to control room operators at all levels, including supervisors.

Published evidence summary
According to gov.uk (Feb 2025), all fire and rescue services have completed regular refresher training for control room operators at all levels, including supervisors, specifically on communicating fire survival guidance. According to LFB Commissioner Andy Roe's announcement in March 2024, the LFB had completed all recommendations directed to the organisation. HM Inspectorate of Constabulary and Fire & Rescue Services rated LFB as 'outstanding' for responding to major and multi-agency incidents in November 2024, noting significant improvements since January 2022.
London Fire Brigade (Primary)
View Details
P1-16
Accepted
Develop policies for handling multiple FSG calls
Recommendation

All fire and rescue services develop policies for handling a large number of Fire Survival Guidance (FSG) calls simultaneously.

Published evidence summary
According to gov.uk (Feb 2025), all fire and rescue services have developed policies for handling a large number of Fire Survival Guidance (FSG) calls simultaneously. The National Fire Chiefs Council (NFCC) had committed to developing national guidance and training products for all 43 fire and rescue services in England following its acceptance of the Phase 1 recommendations in January 2020. HM Inspectorate of Constabulary and Fire & Rescue Services noted in November 2024 that LFB's understanding of risk had improved.
National Fire Chiefs Council (Primary)
View Details
P1-17
Accepted
Electronic FSG recording and display systems
Recommendation

Electronic systems be developed to record FSG information in the control room and display it simultaneously at the bridgehead and in any command units.

Published evidence summary
According to gov.uk (Feb 2025), all fire and rescue services have developed electronic systems to record Fire Survival Guidance (FSG) information in the control room and display it simultaneously to all relevant staff, including at the bridgehead and in command units. According to the National Fire Chiefs Council (NFCC) in January 2020, it had committed to developing national guidance and training products for all 43 fire and rescue services in England following its acceptance of the Phase 1 recommendations. According to HM Inspectorate of Constabulary and Fire & Rescue Services in November 2024, LFB's understanding of risk had improved.
National Fire Chiefs Council (Primary)
View Details
P1-18
Accepted
Develop stay put to evacuation transition policies
Recommendation

Policies be developed for managing a transition from 'stay put' to 'get out'.

Published evidence summary
According to gov.uk (Feb 2025), all fire and rescue services have developed policies for managing a transition from 'stay put' to 'get out'. The National Fire Chiefs Council (NFCC) had committed to developing national guidance and training products for all 43 fire and rescue services in England following its acceptance of the Phase 1 recommendations in January 2020. HM Inspectorate of Constabulary and Fire & Rescue Services noted in November 2024 that LFB's understanding of risk had improved.
National Fire Chiefs Council (Primary)
View Details
P1-19
Accepted
Train control room staff on evacuation advice changes
Recommendation

Control room staff receive training directed specifically to handling such a change of advice and conveying it effectively to callers.

Published evidence summary
According to gov.uk (Feb 2025), control room staff across all fire and rescue services have received training specifically directed to handling a change of advice from 'stay put' to evacuation and effectively conveying it to callers. The National Fire Chiefs Council (NFCC) had committed to developing national guidance and training products for all 43 fire and rescue services in England following its acceptance of the Phase 1 recommendations in January 2020.
National Fire Chiefs Council (Primary)
View Details
P1-20
Accepted
Investigate inter-control room information sharing
Recommendation

Steps be taken to investigate methods by which assisting control rooms can obtain access to the information available to the host control room.

Published evidence summary
According to gov.uk (Feb 2025), the Multi Agency Incident Transfer (MAIT) system has been rolled out across England, enabling inter-control room information sharing. Additionally, all fire and rescue services have embedded new talk groups in their control rooms, and a national 999 call redistribution plan has been introduced to divert calls during major incidents. HM Inspectorate of Constabulary and Fire & Rescue Services noted in November 2024 that LFB's understanding of risk had improved.
National Fire Chiefs Council (Primary)
View Details
P1-21
Accepted
LAS and MPS review FSG call protocols
Recommendation

The London Ambulance Service and Metropolitan Police Service review their protocols and policies to ensure that their operators can identify FSG calls (as defined by the LFB) and pass them to the LFB as soon as possible.

Published evidence summary
According to gov.uk (Feb 2025), the London Ambulance Service (LAS) and Metropolitan Police Service (MPS) reviewed their protocols and policies to ensure that their operators can identify Fire Survival Guidance (FSG) calls and pass them to the London Fire Brigade (LFB) as soon as possible. The LAS had welcomed the findings and accepted the Phase 1 recommendations in October 2019, committing to this review.
London Ambulance Service NHS Trust (Primary)
View Details
P1-22
Accepted
LFB improve deployment control policies
Recommendation

The LFB develop policies and training to ensure better control of deployments and the use of resources.

Published evidence summary
According to gov.uk (Feb 2025), the London Fire Brigade (LFB) implemented a revised High-Rise Firefighting policy in June 2021, which includes structured briefing procedures for deployment control and resource use. LFB Commissioner Andy Roe announced in March 2024 that the LFB had completed all recommendations directed specifically to the organisation. HM Inspectorate of Constabulary and Fire & Rescue Services rated LFB as 'outstanding' for responding to major and multi-agency incidents in November 2024, noting significant improvements since January 2022.
London Fire Brigade (Primary)
View Details
P1-23
Accepted
Improve crew debrief information systems
Recommendation

The LFB develop policies and training to ensure that better information is obtained from crews returning from deployments and that the information is recorded in a form that enables it to be made available immediately to the incident commander.

Published evidence summary
According to gov.uk (26 February 2025), the London Fire Brigade (LFB) stated that improved systems for obtaining information from crews returning from incidents have been implemented. According to the available evidence, LFB Commissioner Andy Roe announced in March 2024 that the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P1-24
Accepted
Direct control room to incident commander communications
Recommendation

The LFB develop a communication system to enable direct communication between the control room and the incident commander and improve the means of communication between the incident commander and the bridgehead.

Published evidence summary
According to gov.uk (26 February 2025), the London Fire Brigade (LFB) developed a Fire Survival Guidance application, which became live in March 2022, to display information simultaneously to all staff handling an incident. According to LFB Commissioner Andy Roe's announcement in March 2024, the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P1-25
Accepted
Investigate modern control room to bridgehead communications
Recommendation
The LFB investigate the use of modern communication techniques to provide a direct line of communication between the control room and the bridgehead, allowing information to be transmitted directly between the control room and the bridgehead and providing an integrated … Read more
Published evidence summary
According to gov.uk (26 February 2025), the London Fire Brigade (LFB) implemented modern communication techniques to provide direct communication between the control room and the bridgehead. According to LFB Commissioner Andy Roe's announcement in March 2024, the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P1-26
Accepted
Equipment for BA communication in high-rise buildings
Recommendation

The LFB urgently take steps to obtain equipment that enables firefighters wearing helmets and breathing apparatus to communicate with the bridgehead effectively, including when operating in high-rise buildings.

Published evidence summary
According to gov.uk (26 February 2025), the London Fire Brigade (LFB) launched new MSA Breathing Apparatus on 11 March 2024, which provides integrated voice communications for firefighters wearing helmets and breathing apparatus. According to LFB Commissioner Andy Roe's announcement in March 2024, the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P1-27
Accepted
Command support system operational on all units
Recommendation

Urgent steps be taken to ensure that the command support system is fully operative on all command units and that crews are trained in its use.

Published evidence summary
According to gov.uk (26 February 2025), the London Fire Brigade (LFB) upgraded all its command units to ensure the command support system is fully operative. According to LFB Commissioner Andy Roe's announcement in March 2024, the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P1-28
Accepted
National guidelines for high-rise evacuations
Recommendation
The government develop national guidelines for carrying out partial or total evacuations of high-rise residential buildings, such guidelines to include the means of protecting fire exit routes and procedures for evacuating persons who are unable to use the stairs in … Read more
Published evidence summary
According to gov.uk (26 February 2025), National Evacuation Guidelines for carrying out partial or total evacuations of high-rise residential buildings were published on 5 February 2024. According to the National Fire Chiefs Council and Fire and Rescue Services, they are now considering how to use these guidelines to develop their operational guidance.
UK Government (Primary)
View Details
P1-29
Accepted
Fire services develop evacuation policies and training
Recommendation

Fire and rescue services develop policies for partial and total evacuation of high-rise residential buildings and training to support them.

Published evidence summary
According to reports, all 43 fire and rescue services in England, including the London Fire Brigade, completed training on evacuation policies for high-rise residential buildings (gov.uk, 26 February 2025). This action aligns with the National Fire Chiefs Council's commitment to developing national guidance and training products.
National Fire Chiefs Council (Primary)
View Details
P1-30
Accepted in Part
Require evacuation plans for high-rise buildings
Recommendation
The owner and manager of every high-rise residential building be required by law to draw up and keep under regular review evacuation plans, copies of which are to be provided in electronic and paper form to their local fire and … Read more
Published evidence summary
According to UK Parliament, 4 July 2025 and gov.uk, 1 February 2026, the Fire Safety (Residential Evacuation Plans) (England) Regulations 2025 (SI 2025/797) were laid before Parliament on 4 July 2025 and are set to come into force on 6 April 2026. According to UK Parliament, 4 July 2025 and gov.uk, 1 February 2026, these regulations mandate the drawing up and review of building-level evacuation plans for high-rise residential buildings.
UK Government (Primary)
View Details
P1-31
Accepted in Part
Require evacuation alarm systems in high-rise buildings
Recommendation
All high-rise residential buildings (both those already in existence and those built in the future) be equipped with facilities for use by the fire and rescue services enabling them to send an evacuation signal to the whole or a selected … Read more
Published evidence summary
According to reports, statutory guidance (Approved Document B) was amended, and BS 8629 was introduced for evacuation alert systems in all new blocks of flats over 18 metres (gov.uk, 26 February 2025). However, the government noted that evidence for retrofitting existing buildings was insufficient to mandate it, and the overall status was reported as 'In Progress' in February 2026.
UK Government (Primary)
View Details
P1-32
Accepted in Part
Require personal emergency evacuation plans (PEEPs)
Recommendation
The owner and manager of every high-rise residential building be required by law to prepare personal emergency evacuation plans (PEEPs) for all residents whose ability to self-evacuate may be compromised (such as persons with reduced mobility or cognition). Read more
Published evidence summary
According to UK Parliament, 4 July 2025 and gov.uk, 1 February 2026, the Fire Safety (Residential Evacuation Plans) (England) Regulations 2025 were laid on 4 July 2025 and mandate Residential Personal Emergency Evacuation Plans (PEEPs) in high-rise and higher-risk buildings, coming into force on 6 April 2026. According to UK Parliament, 4 July 2025 and gov.uk, 1 February 2026, however, full completion of this recommendation, which requires PEEPs for all residents needing them regardless of building height, awaits further primary legislation.
UK Government (Primary)
View Details
P1-33
Accepted in Part
Require PEEP information in premises information box
Recommendation

The owner and manager of every high-rise residential building be required by law to include up-to-date information about persons with reduced mobility and their associated PEEPs in the premises information box.

Published evidence summary
According to gov.uk, 1 February 2026, Residential PEEPs: Guidance for Responsible Persons was published on 2 December 2024, which covers the requirement to include up-to-date PEEP information in the premises information box. According to UK Parliament, 4 July 2025, the Fire Safety (Residential Evacuation Plans) (England) Regulations 2025, laid on 4 July 2025, further mandate this for high-rise buildings.
UK Government (Primary)
View Details
P1-34
Accepted
Equip fire services with smoke hoods
Recommendation

All fire and rescue services be equipped with smoke hoods to assist in the evacuation of occupants through smoke-filled exit routes.

Published evidence summary
According to gov.uk (26 February 2025), all 43 fire and rescue services in England have acquired smoke hoods, which are operationally available with trained staff to assist in the evacuation of occupants through smoke-filled exit routes. This action aligns with the National Fire Chiefs Council's commitment to developing national guidance.
National Fire Chiefs Council (Primary)
View Details
P1-35
Accepted
Require clear floor number markings in high-rise buildings
Recommendation

In all high-rise buildings floor numbers be clearly marked on each landing within the stairways and in a prominent place in all lobbies in such a way as to be visible both in normal conditions and in low lighting or smoky conditions.

Published evidence summary
According to gov.uk (26 February 2025), the Fire Safety (England) Regulations 2022 (SI 2022/1166), which came into force on 23 January 2023, require responsible persons to install clear wayfinding signage, including floor numbers, on each stairway landing in high-rise buildings, visible in low lighting conditions.
UK Government (Primary)
View Details
P1-36
Accepted
Require understandable fire safety instructions
Recommendation
The owner and manager of every residential building containing separate dwellings (whether or not it is a high-rise building) be required by law to provide fire safety instructions (including instructions for evacuation) in a form that the occupants of the … Read more
Published evidence summary
According to gov.uk (26 February 2025), the Fire Safety (England) Regulations 2022 (SI 2022/1166) require the owner and manager of residential buildings containing separate dwellings to provide annual fire safety instructions, including evacuation procedures, in a form that occupants can reasonably understand.
UK Government (Primary)
View Details
P1-37
Accepted
Urgent fire door inspections required
Recommendation

The owner and manager of every residential building containing separate dwellings (whether or not they are high-rise buildings) carry out an urgent inspection of all fire doors to ensure that they comply with applicable legislative standards.

Published evidence summary
According to the available evidence, the Fire Safety (England) Regulations 2022 introduced a legal requirement for owners and managers of residential buildings to carry out quarterly checks on common area fire doors and report the results. According to the available evidence, this action followed the government's acceptance of the recommendation in January 2020 and its commitment to new duties through the Fire Safety Bill and Building Safety Bill. According to the government, the completion of this recommendation was confirmed in February 2025.
Building Owners and Managers (Primary)
View Details
P1-38
Accepted in Part
Require quarterly fire door checks
Recommendation
The owner and manager of every residential building containing separate dwellings (whether or not they are high-rise buildings) be required by law to carry out checks at not less than three-monthly intervals to ensure that all fire doors are fitted … Read more
Published evidence summary
According to the government, the Fire Safety (England) Regulations 2022 established a legal requirement for annual best-effort checks on flat entrance doors in residential buildings. According to the government, this action partially addresses the recommendation for checks at not less than three-monthly intervals to ensure fire doors are fitted with effective self-closing devices. According to the government, the government had accepted the recommendation in principle in January 2020, committing to new duties via the Fire Safety Bill and Building Safety Bill.
UK Government (Primary)
View Details
P1-39
Accepted in Part
Require compliant flat entrance doors where unsafe cladding exists
Recommendation
All those who have responsibility in whatever capacity for the condition of the entrance doors to individual flats in high-rise residential buildings, whose external walls incorporate unsafe cladding, be required by law to ensure that such doors comply with current … Read more
Published evidence summary
According to the available evidence, the Fire Safety Act 2021 and the Fire Safety (England) Regulations 2022 established a legal requirement for responsible persons to ensure that flat entrance doors in high-rise residential buildings with unsafe cladding comply with current standards. According to the available evidence, this action followed the government's acceptance of the recommendation in principle in January 2020, committing to new duties through the Fire Safety Bill and Building Safety Bill. According to the government, the completion of this recommendation was confirmed in February 2025.
UK Government (Primary)
View Details
P1-40
Accepted
Communicate Major Incident declarations to all responders
Recommendation

Each emergency service must communicate the declaration of a Major Incident to all other Category 1 Responders as soon as possible.

Published evidence summary
According to the available evidence, the Joint Emergency Services Interoperability Principles (JESIP) Joint Doctrine was updated in October 2021 to require each emergency service to communicate Major Incident declarations to all other Category 1 responders as soon as possible. According to the available evidence, this action followed the government's acceptance of the recommendation in principle in January 2020. According to the government, the completion of this recommendation was confirmed in February 2025.
UK Government (Primary)
View Details
P1-41
Accepted
Establish inter-service control room communications
Recommendation

On the declaration of a Major Incident clear lines of communication must be established as soon as possible between the control rooms of the individual emergency services.

Published evidence summary
According to the government, the Joint Emergency Services Interoperability Principles (JESIP) Joint Doctrine was updated in October 2021 to mandate that clear lines of communication must be established as soon as practicable between the control rooms of individual emergency services following a Major Incident declaration. According to the government, this action addresses the government's acceptance of the recommendation in principle in January 2020. According to the government, the completion of this recommendation was confirmed in February 2025.
UK Government (Primary)
View Details
P1-42
Accepted
Designate single point of contact in control rooms
Recommendation

A single point of contact should be designated within each control room to facilitate such communication.

Published evidence summary
According to the Joint Emergency Services Interoperability Principles (JESIP) Joint Doctrine updated in October 2021, a single point of contact within each control room must be designated to facilitate inter-service communication during Major Incidents. This action addresses the government's acceptance of the recommendation in principle in January 2020. According to the government's February 2025 update, this recommendation was completed.
UK Government (Primary)
View Details
P1-43
Accepted
Use METHANE messages for Major Incidents
Recommendation
A 'METHANE' (Major incident declared, Exact location, Type of incident, Hazards, Access, Number and type of casualties, Emergency services present and required) message should be sent as soon as possible by the emergency service declaring a Major Incident. Read more
Published evidence summary
According to the government, the Joint Emergency Services Interoperability Principles (JESIP) Joint Doctrine was updated in October 2021, establishing the use of METHANE messages as standard for all Major Incidents. According to the government, this ensures that the emergency service declaring a Major Incident sends a structured message containing key information as soon as possible, aligning with the government's acceptance of the recommendation in principle in January 2020. According to the government, the completion of this recommendation was confirmed in February 2025.
UK Government (Primary)
View Details
P1-44
Accepted
Investigate LFB-MPS-LAS system compatibility
Recommendation

Steps be taken to investigate the compatibility of the LFB systems with those of the MPS and the LAS with a view to enabling all three emergency services' systems to read each other's messages.

Published evidence summary
According to reports, the Multi Agency Incident Transfer (MAIT) system has been established, enabling electronic information transfer between the control rooms of the London Fire Brigade (LFB), Metropolitan Police Service (MPS), and London Ambulance Service (LAS). This system addresses the recommendation to investigate and improve system compatibility for inter-service message exchange. LFB Commissioner Andy Roe stated in March 2024 that the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P1-45
Accepted in Part
NPAS helicopter datalink encryption standards
Recommendation

Steps be taken to ensure that the airborne datalink system on every NPAS helicopter observing an incident which involves one of the other emergency services defaults to the National Emergency Service user encryption.

Published evidence summary
According to the available evidence, steps have been taken to ensure that the airborne datalink system on National Police Air Service (NPAS) helicopters meets encryption standards for secure information sharing, specifically defaulting to the National Emergency Service user encryption. According to the available evidence, this action addresses the government's partial acceptance of the recommendation in principle in January 2020. According to the government's February 2025 update, this recommendation was completed.
UK Government (Primary)
View Details
P1-46
Accepted
Improve survivor information collection and sharing
Recommendation

The LFB, the MPS, the LAS and the London local authorities all investigate ways of improving the collection of information about survivors and making it available more rapidly to those wishing to make contact with them.

Published evidence summary
According to LFB Commissioner Andy Roe's March 2024 statement, London's Major Incidents Procedures Manual, published in November 2021, and subsequent guidance address the improvement of survivor information collection and sharing among the London Fire Brigade (LFB), Metropolitan Police Service (MPS), London Ambulance Service (LAS), and London local authorities. According to LFB Commissioner Andy Roe's March 2024 statement, this action aligns with LFB's acceptance of the recommendation in January 2020. According to LFB Commissioner Andy Roe's March 2024 statement, LFB Commissioner Andy Roe stated in March 2024 that the LFB had completed all recommendations directed specifically to them.
London Fire Brigade (Primary)
View Details
P2-1
Accepted in Part
Establish single construction industry regulator
Recommendation

That the government draw together under a single regulator all the functions relating to the construction industry to which we have referred. (113.6)

Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), building safety functions were transferred from the Health and Safety Executive to a newly created arms-length body via a November Statutory Instrument. According to the Gov.uk progress update (1 Feb 2026), this Building Safety Regulator is operating under interim leadership and is making operational changes to expedite building control approval decisions. According to the Grenfell Tower Inquiry Phase 2 Report: Government response (26 Feb 2025), the government accepted this recommendation in principle, with exceptions for product testing, certification, and issuing compliance certificates.
UK Government (Primary)
View Details
P2-2
Accepted
Review Building Safety Act higher-risk building definition
Recommendation

That the definition of a higher-risk building for the purposes of the Building Safety Act be reviewed urgently. (113.7)

Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), the Building Safety Regulator completed an initial review of the definition of a higher-risk building, concluding that the current definition appropriately reflects the available evidence on fire spread and structural failure risks. The Gov.uk progress update (1 Feb 2026) also stated that no changes to the regime's scope were recommended at present, and an ongoing review mechanism has been established.
UK Government (Primary)
View Details
P2-3
Accepted
Consolidate fire safety functions under single department
Recommendation

That the government bring responsibility for the functions relating to fire safety currently exercised by MHCLG, the Home Office and the Department for Business and Trade into one department under a single Secretary of State. (113.8)

Published evidence summary
According to the Gov.uk progress update, 2026-02-01, the government transferred all fire functions from the Home Office to MHCLG, effective 1 April 2025, with full staff transfer completed on 1 July 2025 and final budget transfers in January 2026. According to the Gov.uk progress update, 2026-02-01, this action consolidated fire-related responsibilities under a single department, exceeding the recommendation's scope by transferring all fire functions rather than solely fire safety responsibilities (Gov.uk progress update, 2026-02-01).
UK Government (Primary)
View Details
P2-4
Accepted
Appoint Chief Construction Adviser
Recommendation
That the Secretary of State appoint a Chief Construction Adviser with a sufficient budget and staff to provide advice on all matters affecting the construction industry, including: a) monitoring all aspects of the department's work relating to the Building Regulations … Read more
Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), Thouria Istephan was appointed as interim Chief Construction Adviser in September 2025 for a 12-month, part-time period via a direct ministerial process. The report also states that the process for appointing a permanent Chief Construction Adviser has commenced, with an appointment expected in September 2026.
UK Government (Primary)
View Details
P2-5
Accepted
Review statutory guidance and Approved Document B
Recommendation

That the statutory guidance generally, and Approved Document B in particular, be reviewed accordingly and a revised version published as soon as possible. (113.11)

Published evidence summary
According to available information, the Building Safety Regulator is undertaking a review of statutory guidance, including Approved Document B, with interim findings published in summer 2025 and comprehensive recommendations anticipated in 2026. According to updates, Approved Document B has undergone multiple updates since 2017, and a six-member expert panel was appointed on 31 July 2025 to guide the ongoing review. A consultation on further changes to Approved Document B was planned for autumn 2025.
UK Government (Primary)
View Details
P2-6
Accepted
Add legal requirements warning to statutory guidance
Recommendation

That a revised version of the guidance contain a clear warning in each section that the legal requirements are contained in the Building Regulations and that compliance with the guidance will not necessarily result in compliance with them. (113.12)

Published evidence summary
According to the Building Safety Regulator, this recommendation is being addressed as part of the broader review of statutory guidance and Approved Document B, led by the Building Safety Regulator. According to the same source, the review aims to improve clarity in Building Regulations guidance, with interim findings published in summer 2025 and comprehensive recommendations expected in 2026.
UK Government (Primary)
View Details
P2-7
Accepted
Reconsider compartmentation in Approved Document B
Recommendation
New materials and methods of construction and the practice of overcladding existing buildings make the existence of effective compartmentation a questionable assumption and we recommend that it be reconsidered when Approved Document B is revised. (113.13) Read more
Published evidence summary
According to reports, the reconsideration of compartmentation guidance is being addressed through the ongoing review of Approved Document B, led by the Building Safety Regulator. A six-member expert panel was appointed on 31 July 2025 to guide this review, which includes examining new materials and construction methods.
UK Government (Primary)
View Details
P2-8
Accepted
Require fire engineer calculations for fire spread and evacuation
Recommendation
Calculating the likely rate of fire spread and the time required for evacuation, including the evacuation of those with physical or mental impairments, are matters for a qualified fire engineer. We do not think that it would be helpful to … Read more
Published evidence summary
According to the Building Safety Regulator, the development of guidance requiring fire engineer calculations for fire spread and evacuation is occurring through the ongoing Approved Document B review. Industry engagement is exploring enhancements to external wall fire spread guidance as part of this review.
UK Government (Primary)
View Details
P2-9
Accepted
Include academics on statutory guidance advisory bodies
Recommendation
That, as far as possible, membership of bodies advising on changes to the statutory guidance should include representatives of the academic community as well as those with practical experience of the industry (including fire engineers) chosen for their experience and … Read more
Published evidence summary
According to the Building Safety Act 2022, the Building Advisory Committee (BAC) was established under the Building Safety Act 2022, and it is supported by thematic working groups, such as the Approved Document B Fire Safety Working Group. According to the same Act, these bodies include substantial academic and professional representation, incorporating a diverse range of expertise into the statutory guidance review process.
UK Government (Primary)
View Details
P2-10
Accepted
Require fire safety strategy from registered fire engineer at Gateway 2
Recommendation
That it be made a statutory requirement that a fire safety strategy produced by a registered fire engineer to be submitted with building control applications (at Gateway 2) for the construction or refurbishment of any higher-risk building and for it … Read more
Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), a fire safety strategy is already required with building control applications for higher-risk buildings. The Building Safety Regulator is considering how to clarify existing guidance regarding these requirements, according to the same update. The update also states that further engagement with the sector and experts is ongoing to reconcile perspectives on strengthened fire safety requirements.
UK Government (Primary)
View Details
P2-11
Accepted
Develop new test methods for evacuation strategy assessments
Recommendation
Assessing whether an external wall system can support a particular evacuation strategy is difficult because the necessary information is not always available. We therefore recommend that steps be taken in conjunction with the professional and academic community to develop new … Read more
Published evidence summary
According to the Gov.uk progress update, 1 Feb 2026, professional and academic collaboration is continuing on the development of external wall testing methods (Gov.uk progress update, 1 Feb 2026). According to the Gov.uk progress update, 1 Feb 2026, this work is part of an ongoing statutory guidance review that is examining the structure of Approved Documents (Gov.uk progress update, 1 Feb 2026).
UK Government (Primary)
View Details
P2-12
Accepted
Clarify BS 9414 limitations requiring fire engineer assessment
Recommendation

BS 9414 should be approached with caution and we recommend that the government make it clear that it should not be used as a substitute for an assessment by a suitably qualified fire engineer. (113.18)

Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), this recommendation is being addressed as part of a broader statutory guidance review. According to the Gov.uk progress update (1 Feb 2026), an expert panel was appointed on 31 July 2025 to guide the Building Safety Regulator-led review, with comprehensive recommendations expected in 2026.
UK Government (Primary)
View Details
P2-13
Accepted in Part
Make construction regulator responsible for product conformity certificates
Recommendation
That the construction regulator should be responsible for assessing the conformity of construction products with the requirements of legislation, statutory guidance and industry standards and issuing certificates as appropriate. We should expect such certificates to become pre-eminent in the market. … Read more
Published evidence summary
According to the Gov.uk progress update, 1 Feb 2026, a Construction Products Reform Green Paper was published, proposing system-wide reform for construction product regulation (Gov.uk progress update, 1 Feb 2026). According to the Gov.uk progress update, 1 Feb 2026, these proposals include licensing requirements for conformity assessment bodies, statutory code obligations, strengthened UKAS oversight, and national regulator enforcement powers against non-compliant products (Gov.uk progress update, 1 Feb 2026).
UK Government (Primary)
View Details
P2-14
Accepted in Part
Require test results disclosure and transparency for construction products
Recommendation
a) that copies of all test results supporting any certificate issued by the construction regulator be included in the certificate; b) that manufacturers be required to provide the construction regulator with the full testing history of the product or material … Read more
Published evidence summary
According to the Gov.uk progress update on 1 Feb 2026, a Construction Products Reform White Paper is currently in development and is expected before Spring 2026. The Gov.uk progress update states that this White Paper will incorporate proposals addressing product testing and conformity assessment, following analysis of responses to the green paper consultation and ongoing sector engagement.
UK Government (Primary)
View Details
P2-15
Accepted
Establish legal recognition and regulation of fire engineer profession
Recommendation
That the profession of fire engineer be recognised and protected by law and that an independent body be established to regulate the profession, define the standards required for membership, maintain a register of members and regulate their conduct. (113.25) Read more
Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), an expert panel was convened to address the regulation of the fire engineer profession and competence expectations. The Gov.uk progress update (1 Feb 2026) also stated that an authoritative statement on fire engineer competence was published on 17 December 2025, alongside a next steps paper outlining key principles for future profession regulation.
UK Government (Primary)
View Details
P2-16
Accepted
Increase Masters-level fire engineering course places
Recommendation

That the government take urgent steps to increase the number of places on high-quality masters level courses in fire engineering accredited by the professional regulator. (113.25)

Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), work from the expert panel addressing fire engineer profession regulation includes master's course expansion and education pathway development. This development is being undertaken in collaboration with industry and professional bodies, according to the Gov.uk progress update (1 Feb 2026).
UK Government (Primary)
View Details
P2-17
Accepted
Define competent fire engineer knowledge and skills
Recommendation
That the government convene a group of practitioner and academic fire engineers and such other professionals as it thinks fit to produce an authoritative statement of the knowledge and skills to be expected of a competent fire engineer. Such a … Read more
Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), an authoritative statement on fire engineer competence was published on 17 December 2025. According to the Gov.uk progress update (1 Feb 2026), this statement was released alongside a next steps paper outlining key principles for future profession regulation.
UK Government (Primary)
View Details
P2-18
Accepted
Develop fire engineering courses for construction professionals
Recommendation
That the government, working in collaboration with industry and professional bodies, encourage the development of courses in the principles of fire engineering for construction professionals and members of the fire and rescue services as part of their continuing professional development. … Read more
Published evidence summary
According to the Gov.uk progress update, 1 Feb 2026, the framework for fire engineering regulation is being addressed through the work of an expert panel (Gov.uk progress update, 1 Feb 2026). According to the Gov.uk progress update, 1 Feb 2026, continuing professional development course development is ongoing in collaboration with industry and professional bodies (Gov.uk progress update, 1 Feb 2026).
UK Government (Primary)
View Details
P2-19
Accepted
Review architect education and training for fire safety
Recommendation
We recognise that both the Architects Registration Board (ARB) and the Royal Institute of British Architects (RIBA) have taken steps since the Grenfell Tower fire to improve the education and training of architects. We recommend that they should review the … Read more
Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), the Royal Institute of British Architects (RIBA) is advancing its education, training, and competence approach, with a comprehensive review of its Code of Practice underway. RIBA's Education and Professional Development Framework, revised post-Grenfell, is undergoing review with implementation expected in 2026, and mandatory Health and Life Safety competence tests were introduced in 2025, according to the Gov.uk progress update (1 Feb 2026).
ARB/RIBA (Primary)
View Details
P2-20
Accepted
Require principal designer compliance statement at Gateway 2
Recommendation
That it be made a statutory requirement that an application for building control approval in relation to the construction or refurbishment of a higher-risk building (Gateway 2) be supported by a statement from a senior manager of the principal designer … Read more
Published evidence summary
According to the Gov.uk progress update, 1 Feb 2026, a statutory requirement proposal mandates that a senior manager of the principal designer must provide a statement with building control approval applications, confirming that all reasonable steps were taken to ensure design compliance with Building Regulations (Gov.uk progress update, 1 Feb 2026). According to the Gov.uk progress update, 1 Feb 2026, the government is considering whether this requirement should extend beyond higher-risk buildings (Gov.uk progress update, 1 Feb 2026).
UK Government (Primary)
View Details
P2-21
Accepted
Introduce licensing scheme for principal contractors
Recommendation
That a licensing scheme operated by the construction regulator be introduced for principal contractors wishing to undertake the construction or refurbishment of higher-risk buildings and that it be a legal requirement that any application for building control approval for the … Read more
Published evidence summary
According to the Gov.uk progress update (1 Feb 2026), a review of the new dutyholder regime is underway, with industry roundtables gathering perspectives on the scope and operational design of a licensing scheme for principal contractors. Analysis of these insights is informing the development of a policy framework, including criteria for licensing alignment with dutyholder requirements and withdrawal for non-compliance, according to the Gov.uk progress update (1 Feb 2026).
UK Government (Primary)
View Details
P2-22
Accepted
Independent panel review of building control commercial interests
Recommendation

That the government appoint an independent panel to consider whether it is in the public interest for building control functions to be performed by those who have a commercial interest in the process. (113.37)

Published evidence summary
According to the Gov.uk progress update, 2026-02-01, an Independent Building Control Panel is currently developing recommendations regarding whether building control functions should remain with commercially interested bodies and if a national authority should perform all functions. According to the Gov.uk progress update, 2026-02-01, the panel's final report is expected in the coming months, with a formal government response anticipated in early 2026 (Gov.uk progress update, 2026-02-01).
UK Government (Primary)
View Details
P2-23
Accepted
Consider national building control authority
Recommendation

We recommend that the same panel consider whether all building control functions should be performed by a national authority. (113.38)

Published evidence summary
According to the Gov.uk progress update (2026-02-01), an Independent Building Control Panel is currently developing recommendations, including whether all building control functions should be performed by a national authority. According to the Gov.uk progress update (2026-02-01), the panel's final report is expected in the coming months, with a formal government response anticipated in early 2026.
UK Government (Primary)
View Details
P2-24
Accepted
Create cladding materials library for designers
Recommendation
We have referred to the Cladding Materials Library set up by the University of Queensland, which could form the basis of a valuable source of information for designers of buildings in general. We recommend that the construction regulator sponsor the … Read more
Published evidence summary
According to the Gov.uk progress update, 2026-02-01, the government is developing a Construction Products Reform White Paper, expected before Spring 2026, which will inform proposals for a materials and products information library or equivalent platform. According to the Gov.uk progress update, 2026-02-01, this initiative aims to provide better access to information, resources, and test results for designers (Gov.uk progress update, 2026-02-01).
UK Government (Primary)
View Details
P2-25
Accepted in Part
Maintain public record of inquiry recommendations
Recommendation
That it be made a legal requirement for the government to maintain a publicly accessible record of recommendations made by select committees, coroners and public inquiries together with a description of the steps taken in response. If the government decides … Read more
Published evidence summary
According to the Gov.uk progress update (2026-02-01) and the Official government response (26 February 2025), Public Inquiries dashboards were published on GOV.UK in July 2025, tracking recommendations from the Grenfell Tower Inquiry Phase 2, Infected Blood, Manchester Arena, and COVID-19 Inquiries. These sources state that these dashboards are updated quarterly, with the most recent update on 14 November 2025, and are planned to evolve to include future inquiry recommendations.
UK Government (Primary)
View Details
P2-26
Accepted
Establish mandatory fire risk assessor accreditation
Recommendation
That the government establish a system of mandatory accreditation to certify the competence of fire risk assessors by setting standards for qualification and continuing professional development and such other measures as may be considered necessary or desirable. We think it … Read more
Published evidence summary
According to the Gov.uk progress update, 2026-02-01, a consultation on a fire risk assessor competence accreditation system is launching in early 2026, proposing mandatory verification of competence by a UKAS-accredited Certification Body. According to the Gov.uk progress update, 2026-02-01, this consultation aims to establish common competence standards and develop a professional pathway (Gov.uk progress update, 2026-02-01).
UK Government (Primary)
View Details
P2-27
Accepted
Standardise fire control switches and keys
Recommendation
We are not in a position to determine whether greater standardisation of the fire control switches and keys is required. We therefore recommend that the government seeks urgent advice from the Building Safety Regulator and the National Fire Chiefs Council … Read more
Published evidence summary
According to the Gov.uk progress update, 2026-02-01, the National Fire Chiefs Council (NFCC) and Building Safety Regulator (BSR) finalised their position on measures for appropriate lift key guidance and standardisation, with updated guidance published on the NFCC website on 23 October 2025. According to the Gov.uk progress update, 2026-02-01, a meeting on 31 October 2025 confirmed BSR internal consideration of these measures (Gov.uk progress update, 2026-02-01).
UK Government (Primary)
View Details
P2-28
Accepted in Part
Require gas valve accessibility inspections every three years
Recommendation
That every gas transporter be required by law to check the accessibility of each [pipeline isolation] valve on its system at least once every three years and to report the results of that inspection to the Health and Safety Executive … Read more
Published evidence summary
According to the Gov.uk progress update (2026-02-01), the Health and Safety Executive (HSE) developed a delivery plan, agreed in September 2025, to establish a baseline for pipeline isolation valve access and consider risk-based inspection approaches. According to the Gov.uk progress update (2026-02-01), targeted stakeholder engagement is scheduled to commence in March 2026 to inform this work.
UK Government (Primary)
View Details
P2-29
Accepted in Part
Establish independent College of Fire and Rescue
Recommendation
That the government establish [an independent College of Fire and Rescue] immediately with sufficient resources to provide the following services nationally: a) practical training at all levels supplementary to that provided by individual fire and rescue services; b) education in … Read more
Published evidence summary
According to the Gov.uk progress update (2026-02-01), the government is progressing with plans to establish an independent College of Fire and Rescue, with a consultation on its functions and structure planned by May 2026. The update notes that a task and finish group has met six times to discuss aims, functions, delivery, and funding models for the college.
UK Government (Primary)
View Details
P2-30
Accepted in Part
College to have permanent staff and training facilities
Recommendation
That [the college] should have a permanent staff of sufficient size to manage its operations and develop its functions in response to the demands of fire and rescue services nationally and the requirements of the board. The college will need … Read more
Published evidence summary
According to the Gov.uk progress update, 2026-02-01, the provision of permanent staff and training facilities for the proposed College of Fire and Rescue will be addressed through a consultation on the college's structure and delivery, which is planned by May 2026 (Gov.uk progress update, 2026-02-01).
UK Government (Primary)
View Details
P2-31
Accepted
Inspect London Fire Brigade control room operations
Recommendation
That His Majesty's Inspectorate of Constabulary and Fire and Rescue Services (the Inspectorate) inspect the London Fire Brigade as soon as reasonably possible to assess and report on: a) the extent to which the control room is now integrated into … Read more
Published evidence summary
According to the Gov.uk progress update, 2026-02-01, His Majesty's Inspectorate of Constabulary and Fire and Rescue Services (HMICFRS) inspected the London Fire Brigade (LFB) in February 2024, publishing its findings in November 2024. According to the Gov.uk progress update, 2026-02-01, the inspection found that LFB had made significant improvements in performance since January 2022, demonstrating enhanced risk understanding and outstanding major incident response (Gov.uk progress update, 2026-02-01).
HMICFRS (Primary)
View Details
P2-32
Accepted
Inspect London Fire Brigade incident commander training
Recommendation
That as soon as reasonably possible the Inspectorate inspect the London Fire Brigade to examine and report on the arrangements it has in place for assessing the training of incident commanders at all levels and their continuing competence, whether by … Read more
Published evidence summary
According to the Gov.uk progress update (2026-02-01), the arrangements for assessing the training and continuing competence of London Fire Brigade incident commanders were covered by the His Majesty's Inspectorate of Constabulary and Fire and Rescue Services (HMICFRS) inspection in February 2024, with findings published in November 2024. The HMICFRS Round 3 inspection confirmed that incident commander training assessment arrangements are in place.
HMICFRS (Primary)
View Details
P2-33
Accepted
Inspect London Fire Brigade information management systems
Recommendation
That as soon as reasonably practicable the Inspectorate inspect the LFB to examine and report on its arrangements for collecting, storing and distributing information in accordance with section 7(2)(d) of the Fire and Rescue Services Act 2004, and in particular … Read more
Published evidence summary
According to the Gov.uk progress update (2026-02-01), the London Fire Brigade's arrangements for collecting, storing, and distributing information, particularly concerning high-risk residential buildings, were addressed through the His Majesty's Inspectorate of Constabulary and Fire and Rescue Services (HMICFRS) inspection in February 2024. The findings of this inspection were published in November 2024.
HMICFRS (Primary)
View Details
P2-34
Accepted
London Fire Brigade to establish lessons learned process
Recommendation
That the London Fire Brigade establish effective standing arrangements for collecting, considering and effectively implementing lessons learned from previous incidents, inquests and investigations. Those arrangements should be as simple as possible, flexible and of a kind that will ensure that … Read more
Published evidence summary
According to the Gov.uk progress update (2026-02-01), the London Fire Brigade (LFB) Operational Policy and Assurance has reviewed and republished its Operational Learning Policy, which now adopts National Fire Chiefs Council (NFCC) Fire Standards. According to the Gov.uk progress update (2026-02-01), this policy aims to provide effective and uncomplicated arrangements for timely operational learning incorporation, supported by a published NFCC Good Practice Guide.
London Fire Brigade (Primary)
View Details
P2-35
Accepted
Consider higher power radios for breathing apparatus
Recommendation
That fire and rescue services that continue to use low power intrinsically safe radios as part of breathing apparatus consider reserving them only for situations in which there is a real risk of igniting flammable gases and generally using radios … Read more
Published evidence summary
According to the Gov.uk progress update (2026-02-01), the National Fire Chiefs Council (NFCC) has developed assurance workshops, with six fire and rescue services having completed them and ten more scheduled for completion by Autumn 2026. According to the Gov.uk progress update (2026-02-01), a learning case report has been compiled, and the London Fire Brigade (LFB) has completed a dual function radio rollout, including training, with over 90% completion for four e-learning modules.
National Fire Chiefs Council (Primary)
View Details
P2-36
Accepted
Provide firefighters with digital radios
Recommendation

That all fire and rescue services give consideration to providing all firefighters with digital radios. (113.60)

Published evidence summary
According to reports, the London Fire Brigade has completed the deployment of digital radios to its firefighters. According to the Gov.uk progress report (1 Feb 2026), the National Fire Chiefs Council (NFCC) is continuing national reporting and assessing digital radio provisions across all fire and rescue services.
National Fire Chiefs Council (Primary)
View Details
P2-37
Accepted
Train firefighters on communications loss response
Recommendation

Since radio communications are inherently unreliable in certain environments, we recommend that firefighters be trained to respond appropriately to the loss of communications and to understand how to restore them. (113.61)

Published evidence summary
According to the Gov.uk progress report of 1 Feb 2026, the National Fire Chiefs Council (NFCC) completed a review of national operational guidance and developed new guidance, which is awaiting approval in April 2026 with publication targeted for June 2026. According to the report, development of learning materials is underway, with quality assurance expected by March 2026, and the London Fire Brigade has completed its work on this recommendation.
National Fire Chiefs Council (Primary)
View Details
P2-38
Accepted
Provide water supply system training to all firefighters
Recommendation
That basic training on the structure and operation of the water supply system, including the different types of hydrants in use and their functions, be given to all firefighters. Training should also be given on effective measures to increase water … Read more
Published evidence summary
According to the Gov.uk progress report of 1 Feb 2026, the National Fire Chiefs Council (NFCC) identified gaps in national training provision on water supply systems after receiving minimal responses from fire and rescue services, with proposals for gap-filling proceeding to the Operational Training and Education Group in January 2026. The London Fire Brigade achieved 90% completion of e-learning with knowledge checks by December 2025, and face-to-face training is ongoing, according to the report.
National Fire Chiefs Council (Primary)
View Details
P2-39
Accepted
Establish water undertaker communication protocols
Recommendation
That all fire and rescue services establish and periodically review an agreed protocol with the statutory water undertakers in their areas to enable effective communication between them in relation to the supply of water for firefighting purposes. (113.63) Read more
Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), the National Fire Chiefs Council (NFCC) engaged with Ofwat, raising concerns about mains compliance with the Environment Department, and responded to an Ofwat consultation in October 2025. The report also states that a revised National Guidance Document, including clear incident support protocols, has been published.
National Fire Chiefs Council (Primary)
View Details
P2-40
Accepted
Amend BS 750 for flow coefficient measurement
Recommendation

That the British Standards Institution amend BS 750 to include a description of the circumstances under which the flow coefficient to which it refers in paragraph 10.2 is to be measured. (113.64)

Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), an expert panel has developed a consultation draft for an amendment to British Standard 750 (BS 750) regarding flow coefficient measurement, with consultation publication expected imminently. The report also states that the amendment's publication is targeted for Q1 2026, pending the volume of responses received.
British Standards Institution (Primary)
View Details
P2-41
Accepted
Consider guidance on firefighter initiative deviations
Recommendation
That National Fire Chiefs Council consider whether, and if so in what circumstances, firefighters should be discouraged from departing from their instructions on their own initiative and provide appropriate training in how to respond to a situation of that kind. … Read more
Published evidence summary
According to the Gov.uk progress report of 1 Feb 2026, the National Fire Chiefs Council (NFCC) completed a review of guidance on crew briefing and debriefing in September 2025. According to the report, a change request process has been initiated, proposing new hazard and control measures for Incident Command guidance, with approval targeted before April 2026 and publication in June 2026.
National Fire Chiefs Council (Primary)
View Details
P2-42
Accepted
Review Civil Contingencies Act intervention powers
Recommendation

That the [Civil Contingencies] Act [2004] be reviewed and consideration be given to granting a designated Secretary of State the power to carry out the functions of a Category 1 responder in its place for a limited period of time. (113.67)

Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), the Cabinet Office completed an initial assessment of intervention powers within the Civil Contingencies Act 2004 and related legislation. The report also states that policy proposals are currently under development for ministerial review.
UK Government (Primary)
View Details
P2-43
Accepted in Part
Require voluntary sector partnerships in contingency planning
Recommendation
Regulation 23 of the Civil Contingencies Act 2004 (Contingency Planning) Regulations 2005 requires a Category 1 responder to have regard when making its plans to the activities of relevant voluntary organisations. We therefore recommend that the regulation be amended to … Read more
Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), a consultation titled "Stronger Partnerships" received 165 responses, and the government published its public response on 16 December 2025. The report also states that the government is now considering regulatory changes and conducting an impact evaluation in 2026.
UK Government (Primary)
View Details
P2-44
Accepted
Consolidate and update emergency preparedness guidance
Recommendation
The current guidance on preparing for emergencies is contained in several documents, all of which are unduly long and in some respects out of date. We recommend that the guidance be revised, reduced in length and consolidated in one document … Read more
Published evidence summary
According to the Gov.uk progress report of 1 Feb 2026, an initial review of emergency preparedness guidance identified priorities for consolidation and withdrawal, and a new GOV.UK page was launched to centralise resilience guidance. Ongoing stakeholder engagement is planned for further prioritisation and updates, according to the report.
UK Government (Primary)
View Details
P2-45
Accepted
Add humanitarian considerations as ninth response principle
Recommendation

That regard for humanitarian considerations be expressly recognised by making it the ninth principle of effective response and recovery. (113.69)

Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), the Cabinet Office developed a National Resilience Standard on Human Aspects, which supports responders and Local Resilience Forums in addressing the psychosocial needs of individuals affected by emergencies.
UK Government (Primary)
View Details
P2-46
Accepted
Revise London Gold arrangements guidance
Recommendation
Events demonstrated, however, that there is a need for a clearer understanding of the nature of the London Gold arrangements, in particular in situations in which a single borough is affected. We therefore recommend that the guidance on the operation … Read more
Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), updated London Local Authority Gold Operating procedures were circulated on 30 September 2025, and regional gold training commenced in October 2025, with four courses planned through April 2026. The report also states that an update to the London Local Authority Concept of Operations is targeted for completion by 31 March 2026.
London Authorities (Primary)
View Details
P2-47
Accepted
Local resilience forums to adopt national standards
Recommendation

That local resilience forums adopt national standards to ensure effective training, preparation and planning for emergencies and adopt independent auditing schemes to identify deficiencies and secure compliance. (113.71)

Published evidence summary
According to the Gov.uk progress report of 1 Feb 2026, all five Local Resilience Forum (LRF) trailblazers are continuing implementation, with four Chief Resilience Officers now in post. A national working group has held four meetings to design a peer review protocol, which is planned for testing by March 2026, according to the report.
UK Government (Primary)
View Details
P2-48
Accepted in Part
Verify training quality of Category 1 responders
Recommendation

That a mechanism be introduced for independently verifying the frequency and quality of training provided by local authorities and other Category 1 responders. (113.71)

Published evidence summary
According to the Gov.uk progress report of 1 Feb 2026, the Ministry of Housing, Communities and Local Government (MHCLG) identified existing reporting arrangements for resilience training. Collaboration is ongoing with the Local Government Association and the UK Resilience Academy to test proposals with the sector in early 2026, according to the report.
UK Government (Primary)
View Details
P2-49
Accepted
Train all local authority employees on resilience
Recommendation

That local authorities train all their employees, including chief executives, to regard resilience as an integral part of their responsibilities. (113.73)

Published evidence summary
According to the Gov.uk progress report (1 Feb 2026), a partnership training programme is under development by MHCLG, Cabinet Office, LGA, UK Resilience Academy, and SOLACE. The report states that a national curriculum working group met in October 2025, with additional sessions planned for 2026, and rollout to chief executives began in early 2026.
Local Authorities (Primary)
View Details
P2-50
Accepted
Devise displaced person information recording methods
Recommendation
RBKC had no effective means of collecting and recording information about those who had been displaced from the tower and surrounding buildings, including those who were missing. Compiling reliable information of that kind is difficult and the challenges likely to … Read more
Published evidence summary
According to the Ministry of Housing, Communities and Local Government (MHCLG), the government supports this recommendation for local authorities, with the MHCLG engaging with sector partners to determine appropriate guidance approaches for local authority emergency duties. According to the same source, this engagement involves organisations such as the Association of Directors of Adult Social Services, the Association of Directors of Children's Services, and the Local Government Association.
Local Authorities (Primary)
View Details
P2-51
Accepted
Arrange emergency temporary accommodation provision
Recommendation
That all local authorities make such arrangements as are reasonably practicable for enabling them to place people in temporary accommodation at short notice and in ways that meet their personal, religious and cultural requirements. Such arrangements should, as far as … Read more
Published evidence summary
According to the available evidence, the government supports this recommendation, noting that local authorities are already legally obligated under the Housing Act 1996 to re-house people displaced by an emergency. The Ministry of Housing, Communities and Local Government (MHCLG) is engaging with sector partners to develop guidance that will clarify these duties and arrangements for temporary accommodation.
Local Authorities (Primary)
View Details
P2-52
Accepted
Include financial assistance in contingency plans
Recommendation

That all local authorities include in their contingency plans arrangements for providing immediate financial assistance to people affected by an emergency. (113.76)

Published evidence summary
According to the government's position, this recommendation is supported, with the Ministry of Housing, Communities and Local Government (MHCLG) engaging with local authorities and the Local Government Association (LGA). According to available information, this engagement aims to determine appropriate guidance approaches for integrating immediate financial assistance into local authority contingency plans for emergencies.
Local Authorities (Primary)
View Details
P2-53
Accepted
Plan for key worker availability in emergencies
Recommendation
That as part of their planning for emergencies local authorities give detailed consideration to the availability of key workers and the role they are expected to play so that suitable contingency arrangements can be made to ensure, as far as … Read more
Published evidence summary
According to the Ministry of Housing, Communities and Local Government (MHCLG), the government supports this recommendation, specifically regarding social workers, and the MHCLG is collaborating with the Department for Health and Social Care, the Department for Education, and the Local Government Association. According to the same source, this collaboration aims to determine appropriate guidance approaches for ensuring key worker availability and support in emergency planning.
Local Authorities (Primary)
View Details
P2-54
Accepted
Establish effective emergency communication methods
Recommendation

That as part of their emergency planning local authorities make effective arrangements for continuing communication with those who need assistance using the most suitable technology and a range of languages appropriate to the area. (113.77)

Published evidence summary
According to the government, this recommendation is supported, noting that local authorities have existing legal obligations under the Civil Contingencies Act 2004 regarding emergency communication. The Ministry of Housing, Communities and Local Government (MHCLG) is engaging with sector partners to develop guidance that will clarify these duties and establish effective communication methods for people needing assistance during emergencies.
Local Authorities (Primary)
View Details
P2-55
Accepted
Use modern communication for public emergency information
Recommendation
That all local authorities include in their plans for responding to emergencies arrangements for providing information to the public by whatever combination of modern methods of communication are likely to be most effective for the areas for which they are … Read more
Published evidence summary
According to the government's position, this recommendation is supported, highlighting local authorities' existing legal obligations under the Civil Contingencies Act 2004 for providing public information during emergencies. According to available information, the Ministry of Housing, Communities and Local Government (MHCLG) is engaging with sector partners to develop guidance that will clarify these duties and promote the use of modern communication methods.
Local Authorities (Primary)
View Details
P2-56
Accepted
Clarify casualty bureau purpose and limitations
Recommendation

That what in the past has been called by the police a 'casualty bureau' be described in a way that makes it clear that it does not provide information to the public about people affected by the emergency. (113.78)

Published evidence summary
According to the NPCC, the National Police Chiefs' Council (NPCC) has updated the standard operating procedures for the casualty bureau and collaborated with force communication leads to clearly describe its functions to the public. According to the NPCC, this action addresses a similar recommendation from the 2018 Kerslake independent review of the Manchester Arena bombing.
National Police Chiefs Council (Primary)
View Details
P2-57
Accepted
Reconsider Phase 1 recommendations in light of Phase 2
Recommendation

That further consideration be given to the recommendations made in the Phase 1 report in the light of our findings in this report. (113.82)

Published evidence summary
According to the government's response to the Emergency Evacuation Information Sharing Plus (EEIS+) consultation, which was published on 2 December 2024, this recommendation was addressed. Subsequently, The Fire Safety (Residential Evacuation Plans) (England) Regulations 2025 were laid on 4 July 2025, mandating Residential Personal Emergency Evacuation Plans.
UK Government (Primary)
View Details
P2-58
Accepted
Reconsider LGA Guide paragraph 79.11 advice
Recommendation

That the advice contained in paragraph 79.11 of the LGA Guide be reconsidered. (113.83)

Published evidence summary
According to reports, the advice contained in paragraph 79.11 of the LGA Guide was redacted in 2021, and new guidance addressing these issues was published on 2 December 2025. This new guidance is titled 'Residential PEEPs: Guidance for Responsible Persons'.
UK Government (Primary)
View Details