Edinburgh Tram Inquiry

Completed
Chair Lord Hardie Judge / Judiciary
Established 01 Oct 2014
Final Report 12 Sep 2023
Commissioned by Scottish Government

Public inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope. The project cost £776m against an original estimate of £375m and took 5 years longer than planned.

Evidence & Impact
The Edinburgh Tram Inquiry, chaired by Lord Hardie, examined the planning and construction of Edinburgh's tram system, which experienced significant cost overruns and delays. The inquiry published 24 recommendations in August 2023 focusing on project governance, management practices, and legal reforms.

The Scottish Government accepted 14 recommendations (58%), accepted 7 in principle (29%), and placed 3 under consideration (12%). In its November 2023 response, the Government stated that enhanced procedures for documentation management had been embedded within government and that guidance for establishing inquiries was already in development. The Government noted its commitment to collaborative working through the Verity House agreement, whilst maintaining that responsibility for project delivery remains with councils.

City of Edinburgh Council's Chief Executive reported to the Transport and Environment Committee in November 2023, recommending acceptance of several recommendations. Council Leader Cammy Day acknowledged that "serious mistakes were made in the construction of the original tram line" and noted that processes implemented since the original project had helped deliver the successful Trams to Newhaven extension.

The Council reported that scrutiny of ALEOs had "significantly improved" following reviews in 2012 and 2016, resulting in formalised observer roles and increased committee scrutiny. Training on the Member/Officer Protocol was being delivered to senior officers to clarify the distinction between officer and councillor roles.

Three recommendations regarding civil damages provisions and criminal offences for misleading evidence to inquiries remain under consideration by the Scottish Government, which noted that existing remedies may already exist under delictual liability and fraud law.

Whilst both the Scottish Government and City of Edinburgh Council provided initial responses accepting most recommendations, published evidence of specific implementation actions remains limited for many recommendations, particularly those relating to project management expertise requirements, governance structures, and stakeholder co-location practices.
Reforms Attributed to This Inquiry
- Enhanced procedures for minute-taking and documentation management embedded within Scottish Government and Civil Service (Scottish Government statement, November 2023)
- Improved scrutiny arrangements for Arms Length External Organisations (ALEOs) by City of Edinburgh Council, including formalised observer roles and regular committee reporting following 2012 and 2016 reviews
- Member/Officer Protocol training delivered to senior officers at City of Edinburgh Council to clarify distinction between officer and councillor roles
- Guidance for efficient establishment of inquiries developed and shared with recent inquiries (Scottish Government statement, November 2023)
Unfinished Business
- Recommendations on civil damages provisions and criminal statutory offences for misleading evidence to inquiries remain under consideration by Scottish Government
- No published evidence of action on recommendations regarding project management expertise requirements for light rail projects
- No published evidence of progress on recommendations for governance structure guidance and role clarity in major projects
- No published evidence regarding recommendations on co-location of project stakeholders
- No published evidence of updates to guidance on best practices for light rail delivery, despite Scottish Government stating it already operates in line with best practices
AI-generated narrative. Generated 26 Mar 2026 using claude-opus-4. Assessment is indicative, not authoritative.
Live tracking hearings, witnesses and documents synced daily from the inquiry website Open live tracker Search evidence
8 years, 10 months Duration
£13.2m Total Cost
100 Witnesses
160 Hearing Days
7 Core Participants
6,000,000 Documents
961 Report Pages
Government Response

Total Recommendations 24
Data last updated: 16 Nov 2023 · Source
Data verified: 31 Jan 2026 (Claude)
How to read this

Government Response tracks what the government said it would do (accepted, rejected, etc.).

Full methodology

Title Volume Publication Date Tracked recs Links
Edinburgh Tram Inquiry Report Final Report 01 Aug 2023 24
05 Jun 2014
Inquiry Announced

Scottish Ministers established an inquiry into the Edinburgh Tram Project.

Source
03 Jul 2014
Chair Appointed

Lord Hardie appointed as Chair.

08 Sep 2014
Terms of Reference Set

Inquiry to examine why project was delayed and over budget.

09 Mar 2017
Hearings Begin

Evidence hearings commenced.

12 Sep 2023
Final Report Published

Report published with 24 recommendations.

Source
31 Jan 2024
Government Response

Scottish Government response to recommendations.

Recommendations (14)

ETI-5
Accepted
Business Case Timing
Recommendation
Where the Business Case for any future light rail project is based upon an assumption that, prior to the award of the contract for the construction of the infrastructure, certain matters will have been completed (e.g. design, the obtaining of … Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated guidance specifically requiring revised Business Cases where pre-contract assumptions on design, approvals, or utility diversions have not been met has been identified to March 2026.
Scottish Government (Primary)
View Details
ETI-6
Accepted
Optimism Bias in Business Cases
Recommendation

All versions of the Business Case, including any Business Case required as a result of altered assumptions, should include an assessment of risk that takes account of optimism bias in accordance with the current published government guidance.

Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- Scottish Government Green Book supplementary guidance requires consideration of optimism bias in Business Cases, but no published update specifically responding to this recommendation has been identified to March 2026.
Scottish Government (Primary)
View Details
ETI-7
Accepted
External Peer Review
Recommendation
The assessment of risk at each stage mentioned in Recommendation 6 should be the subject of a peer review by external consultants with experience of similar large-scale infrastructure projects in the transportation sector who should submit a report of each … Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published requirement for mandatory external peer review of Business Case risk assessments for large-scale transportation infrastructure projects has been identified to March 2026.
Scottish Government (Primary)
View Details
ETI-9
Accepted
Risk Management Standards
Recommendation
The identification and management of risk should be an integral part of the governance of all major public-sector contracts in future. In identifying and managing risk the following principles should be adopted: • Probabilistic forecasts rather than single-point forecasts should … Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated guidance specifically addressing probabilistic forecasting, early warning detection, and quality-focused evidence for major public sector contracts has been identified to March 2026.
Scottish Government (Primary)
View Details
ETI-12
Accepted
Record Keeping Requirements
Recommendation
For reasons of transparency and accountability for public expenditure, the Scottish Ministers should keep minutes of: • the nature and content of any discussions and the reasons for any decisions taken at all meetings, discussions or telephone conversations, and in … Read more
Published evidence summary
- In November 2023, the Scottish Government stated that "robust and enhanced procedures regarding minute-taking and documentation management have also been embedded within the Government and the Civil Service" (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No independently published assessment of whether the enhanced documentation procedures are operating effectively in relation to publicly funded major projects has been identified to March 2026.
Scottish Government (Primary)
View Details
ETI-13
Accepted
Utility Diversion Planning
Recommendation
The procurement strategy for any future light rail project should make adequate provision for the uncertainties concerning the location of utilities and redundant equipment belonging to present and past utility companies, particularly in urban centres. In particular, although it is … Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated procurement guidance specifically addressing utility location uncertainties, requiring route exposure and clearance before construction, has been identified to March 2026.
Scottish Government (Primary)
View Details
ETI-14
Accepted
Utility Diversion Risk Management
Recommendation
Although some participants in the Inquiry criticised the use of MUDFA to divert utilities in advance of the infrastructure works and advocated the “bow wave” approach to the diversion of utilities that followed the mediation settlement at Mar Hall, I … Read more
Published evidence summary
- In November 2023, the Scottish Government stated it already operates in line with best practices for governance and light rail delivery (Transport Secretary Statement on Edinburgh Tram Inquiry Report, Scottish Government, 2 November 2023).
- No published updated guidance specifically addressing utility diversion risk management approaches has been identified to March 2026.
Scottish Government (Primary)
View Details
ETI-15
Accepted
Qualified Project Management
Recommendation
In recognition of the various difficulties likely to be experienced in the design and construction of a light rail project through a city centre, the promoter and owner of the project should appoint as its procurement and project manager a … Read more
Published evidence summary
- In November 2023, City of Edinburgh Council Leader Cammy Day stated that the Council broadly agreed with Lord Hardie's recommendations and noted improvements had been implemented for the successful delivery of the Trams to Newhaven project (City of Edinburgh Council response, November 2023).
- In a subsequent Council committee report (16 November 2023), the Council noted that the Trams to Newhaven project had demonstrated improved procurement and project management practices (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal framework requiring appointment of experienced permanent employees for light rail project management has been identified to March 2026.
City of Edinburgh Council (Primary)
View Details
ETI-16
Accepted
Design Engagement Process
Recommendation
Immediately following the appointment of the designer, and throughout the design of the project, the designer should engage with the promoter and owner of the project, the procurement and project manager, the local planning authority, the utility companies and interested … Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting improvements had been implemented for Trams to Newhaven (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) acknowledged that the original tram project lacked a single point of contact to coordinate design responses, and that this had been addressed in the Newhaven project (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal guidance requiring continuous engagement between promoters, owners, and planning authorities on design criteria for future light rail projects has been identified to March 2026.
City of Edinburgh Council (Primary)
View Details
ETI-17
Accepted
Governance Structure
Recommendation
The governance structure for the delivery of a major project such as a light rail scheme should follow the published guidance and should ensure that there is clarity regarding the respective roles of the various bodies and individuals involved in … Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting that governance improvements had been implemented for Trams to Newhaven (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) acknowledged difficulties in the governance of the first phase due to complexity in the governance structure and lack of understanding by individuals of their roles and responsibilities (City of Edinburgh Council Committee Report, 16 November 2023).
- No published updated governance framework specifically prohibiting the chairman of a procurement company from also serving as its chief executive has been identified to March 2026.
City of Edinburgh Council (Primary)
View Details
ETI-18
Accepted
Interviews of Key Personnel in Readiness Reviews
Recommendation
As part of their investigations, representatives of OGC undertaking an independent “readiness review” of a publicly funded project and representatives of any person, including representatives of any public body such as Audit Scotland, undertaking a review of the progress of … Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting improvements in communication and reporting had been implemented for Trams to Newhaven (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) stated that the Council agreed to support any future readiness review or audit to ensure clear understanding of progress and reporting (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal framework for mandatory progress reporting and escalation procedures in major publicly funded projects has been identified to March 2026.
City of Edinburgh Council (Primary)
View Details
ETI-19
Accepted
Collaborative Delivery
Recommendation
At all stages of the project there should be a collaborative approach to delivering it. This should include the co-location of representatives from each organisation relevant to the particular stage reached and having an interest in its completion to enable … Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations, noting that co-location of representatives had been successfully adopted on the Trams to Newhaven project (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) acknowledged that co-location had proven advantageous on the Newhaven project (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal requirement for collaborative co-location in future major infrastructure projects has been identified to March 2026.
City of Edinburgh Council (Primary)
View Details
ETI-20
Accepted
Prohibition on Misleading Reports from ALEOs
Recommendation
The directors, employees and consultants of the company responsible for the procurement and delivery of the project as project managers, including an arm’s-length external organisation (“ALEO”) wholly owned by the local authority that is the promoter and owner of the … Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) noted that scrutiny of arm's-length external organisations (ALEOs) had significantly improved since the original tram project, with reviews in 2012 and 2016 strengthening governance arrangements and the Council's relationship with its ALEOs (City of Edinburgh Council Committee Report, 16 November 2023).
- No published formal prohibition on ALEO directors or employees submitting public interest claims without the approval of senior officers of the parent local authority has been identified to March 2026.
City of Edinburgh Council (Primary)
View Details
ETI-21
Accepted
Duty of Officials to Councillors
Recommendation
Local authority officials should be mindful at all times of the distinction in roles between them and councillors, who are solely responsible for strategic decisions, and of their duty to provide accurate reports to councillors to enable them to take … Read more
Published evidence summary
- In November 2023, the Council stated it broadly agreed with Lord Hardie's recommendations (City of Edinburgh Council response, November 2023).
- The Council committee report (16 November 2023) noted that the Council's Member/Officer Protocol highlights the distinction in roles between officials and councillors (City of Edinburgh Council Committee Report, 16 November 2023).
- No published updated guidance specifically requiring accurate reporting to councillors on major project progress has been identified to March 2026.
City of Edinburgh Council (Primary)