CompletedPublic inquiry into why the Edinburgh Trams project was delivered late, over budget, and with a reduced scope. The project cost £776m against an original estimate of £375m and took 5 years longer than planned.
Reports (1) Click to expand
| Title | Volume | Publication Date | Recs | Links |
|---|---|---|---|---|
| Edinburgh Tram Inquiry Report | Final Report | 12 Sep 2023 | 24 |
Timeline (6) Click to expand
Scottish Ministers established an inquiry into the Edinburgh Tram Project.
SourceLord Hardie appointed as Chair.
Inquiry to examine why project was delayed and over budget.
Evidence hearings commenced.
Scottish Government response to recommendations.
Recommendations (14)
Business Case Timing
Where Business Cases assume pre-contract completion of design, approvals, or utility diversions, contract negotiations should await completion; otherwise, a revised Business Case reflecting actual conditions must be prepared before signing.
Optimism Bias in Business Cases
All Business Case versions must include risk assessments accounting for optimism bias per published government guidance.
External Peer Review
Each Business Case risk assessment should undergo peer review by external consultants experienced in large-scale transportation infrastructure, submitting reports sufficiently before contract signature.
Risk Management Standards
Record Keeping Requirements
Utility Diversion Planning
Utility Diversion Risk Management
While acknowledging utility diversion approaches, promoters should demonstrate adequate risk management proposals without prescriptive requirements regarding MUDFA versus bow wave methods.
Qualified Project Management
Project promoters should appoint procurement and project managers with qualified, experienced permanent employees who have successfully delivered similar projects on time and within budget.
Design Engagement Process
Governance Structure
Effective Communication and Reporting
There should be effective communication and reporting at all stages of the project, including accurate progress reports to councillors and stakeholders, with clear escalation procedures for issues that may affect cost, programme or scope.